Data centres in northern Malaysia: Kedah and Penang

What was cancelled, what is running, and what the climate data says about the north.

Contents

Penang has a running data centre; Kulim’s planned one was cancelled. Open DC’s Bayan Lepas campus had about 15 MW energised in September 2026, with its target raised to 100 MW, and Open DC runs 2 MW at Bukit Kayu Hitam in Kedah, growing to 4 MW (TechWire Asia).

Maxland Data’s project at Kulim Hi-Tech Park was cancelled: in May 2026 both of its leases there were mutually rescinded (EdgeProp, 15 May 2026).

About 15 MW
Open DC Bayan Lepas, energised, Sep 2026 (TechWire Asia)
100 MW
Open DC Penang target (TechWire Asia)
May 2026
Kulim Hi-Tech Park leases rescinded (EdgeProp)

Are there data centres in Kulim or Penang?

Data-centre projects in Kedah and Penang
ProjectLocationSizeStatusSource
Open DC PE2Bayan Lepas, PenangAbout 15 MW energised; target 100 MW on a 10-acre campusOperating, expanding(TechWire Asia, Sep 2026)
Open DC D8-1Bukit Kayu Hitam, Kedah2 MW, expanding to 4 MWOperating(TechWire Asia)
AREA Group campusBukit Kayu Hitam, Kedah156 acres; MW not confirmedStatus inconsistent(Baxtel)
Maxland Data / GDCKulim Hi-Tech Park, KedahNo MW ever disclosedCancelled May 2026(EdgeProp)

What happened to the Kulim Hi-Tech Park data-centre project?

It was cancelled. In December 2024 Maxland Data, a subsidiary of Maxland Bhd, leased 4.57 acres in Kulim Hi-Tech Park for 60 years for RM9.95m, with Global Data Centre as partner (The Star); a second unit leased 4.85 acres for RM10.57m for district cooling. In May 2026 both units signed deeds of revocation with the park corporation to rescind the leases by mutual agreement, after a strategic review found the land no longer fit the group’s plans. Partial refunds of about RM653,000 and RM744,000 are expected, and the group’s auditor has flagged a material uncertainty about going concern (EdgeProp, 15 May 2026). Baxtel lists the project as cancelled before construction (Baxtel).

Is northern Malaysia viable for data centres?

The public record cannot settle it: northern grid capacity and water allocations for data centres are not published. The climate data splits the region. Coastal Bayan Lepas is among the mildest districts we measured (18 hours a year above 32°C); inland Kulim is among the hottest (138) and had the second-lowest rain in its driest 60 days (70 mm).

District climate, 2016–2025 (ERA5)
DistrictHours/yr above 30°CAbove 32°CHottest hourRain, averageDriest 60 days
Kulim87213836.1°C3,822 mm70 mm
Bayan Lepas3121834.5°C3,533 mm115 mm

ERA5 reanalysis via Open-Meteo, 2016–2025; hour counts are lower bounds. All districts: cooling climate.

What is not public

We could not confirm these from a published source as of 10 November 2026. Do not assume them:

  • Megawatts for the AREA Group campus
  • Northern grid capacity for data centres
  • Water allocations for data centres in Kedah and Penang

Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.

Sources

Last checked 10 November 2026

Questions

Is there a data centre in Penang?

Yes. Open DC’s Bayan Lepas campus had about 15 MW energised in September 2026, with a 100 MW target.

What happened to the Kulim data-centre project?

Maxland Data’s Kulim Hi-Tech Park leases were mutually rescinded in May 2026; the project is cancelled.