Where AI data centres can be built in Malaysia, and what decides it

Power and water now decide where AI halls go, more than land does. This guide brings the public record together in one place: parliamentary replies, regulator rules, state policy, published land deals and climate data, each with its source.

8.39 GW
Projected 2030 data-centre peak demand, Peninsular Malaysia (ministry figure)
445 MLD
Data-centre water approved for 2025–2030 in Selangor, Johor and Negeri Sembilan
21%
Share of requested water Johor granted data centres in 2024
RM105–150
Per sq ft paid for data-centre land in six published deals

Sources and dates for each figure are in the sections below.

Contents

The short answer

Johor has most of the demand and most of the grid and water stress. Selangor and Negeri Sembilan are the second wave. Sarawak is the low-carbon outlier: hydro power, a grid emission factor about a quarter of the Peninsula’s, and no federal energy-reporting duty. Since February 2026 new applications must be AI-related. Water is now granted per application and often in part. Site-level facts such as spare substation capacity, flood zones and water per plot are not public, so this guide compares states and zones. It does not rank plots.

Three things decide a site

Power
Can TNB connect the load, and when? Green Lane targets 12 months, against 36–48 before it.
Water
How much will the state grant? In 2024, Johor granted 21% of requested volumes and Selangor 28%.
Approval
Does the project count as AI, and does it meet the state’s cooling and water rules?

Last checked 8 November 2026

Power and grid

Power is the binding constraint. The public record is detailed at national and state level and silent at substation level.

Power and grid facts
FactFigureSource
2030 data-centre peak demand, Peninsular8.39 GW, of which Johor 4.42 GW and Selangor 1.48 GWMalay Mail, Oct 2026
Supply capacity approved for data centres12.3 GW (Aug 2026)The Star, Oct 2026
Operating data centres, Peninsular45 on 6.04 GW (Aug 2026); the minister separately cited 57 centres needing 6,237 MWMalay Mail
Booked versus used1,374 MW used of 2,346 MW contracted (58.6%). The minister said operators will have to pay for full contracted capacity; no date or rate givenw.media; The Star
TariffUltra-high-voltage band from 1 Jul 2025: 51.18 sen/kWh peak, 47.09 off-peak, before fuel surcharge. An analyst projects about 66.6 sen/kWh effective if a 7.59 sen surcharge applies from Jan 2027 (a projection, not the current rate)The Star
Renewables ruleAt least 30% renewable energy for the sector, approved Oct 2026. No effective date; framework still being draftedMalay Mail; w.media
Grid connectionTNB Green Lane Pathway targets 12 months instead of 36–48; 33 projects delivered by Mar 2026TNB; The Star
Johor grid stressShortages at 132 kV intake substations in the Sedenak and Nusajaya clusters; Johor is about 51% of Peninsular data-centre demandWood Mackenzie
Grid emission factor (kg CO₂e/kWh, 2024 provisional)Peninsular 0.740 · Sabah 0.539 · Sarawak 0.199Energy Commission, Feb 2026
2030 data-centre peak demand, Peninsular Malaysia
Johor
4.42 GW
Selangor
1.48 GW
Rest of Peninsula
2.49 GW
Peninsular total
8.39 GW

Ministry projection, Oct 2026. A 12.9 GW figure in circulation has no traceable source and is not used.

Operating counts differ by scope (45 centres on 6.04 GW, against 57 centres needing 6,237 MW). We show both.

Last checked 8 November 2026

Water

Water is now rationed per application, and Johor sets what reads as a stricter efficiency bar than the national guideline.

Water facts
FactFigureSource
Share of requested water granted, 2024Johor 21% (6.10 of 29.1 MLD); Selangor 28% (1.61 of 5.71 MLD)EdgeProp
Approved data-centre water, 2025–2030445.04 MLD across Selangor, Johor and Negeri Sembilan (Oct 2026): 389.04 MLD Johor and Selangor, 56 MLD Negeri SembilanThe Star; The Vibes
Approved for sites already operating63.90 MLD (14.36%), as of June 2026The Star
Data-centre water tariffRM5.30–5.38 per m³ across Peninsular Malaysia and Labuan: Johor RM5.33 from 1 Aug 2025, Selangor RM5.31 from 1 Sep 2025, plus a capital contribution for supply worksThe Star; Malay Mail
Reserve marginsJohor about 14.4% (Jun 2026). Selangor fell from 17.4% (Apr 2026) to 16.23% (Aug 2026). The regulator SPAN classes above 15% as highThe Star; Malay Mail
Johor’s rulesA state technical committee vets every application. Allowable WUE 1.8 (unit not published). Reclaimed or alternative water required in some cases. Tier 1 and 2 halls not approved since Nov 2025. Evaporative-cooled sites wait until 2027 for water approvalThe Star; w.media
Reclaimed waterJohor plants: Ulu Tiram 5 MLD (planned to 20), Gelang Patah 4 MLD, fed by treated effluent from Indah Water. Nationally 48.5 MLD now, 118 MLD target by 2030The Star; theSun; Malay Mail
Water requested against granted, 2024

Johor

Requested29.1 MLD
Granted6.10 MLD

Selangor

Requested5.71 MLD
Granted1.61 MLD

Parliamentary reply via EdgeProp.

If Johor’s 1.8 is in litres per kWh (equal to m³ per MWh), it is stricter than MITI’s recommended 2.2. The state has not published the unit.

Last checked 8 November 2026

Approvals

The approval path is public in outline. No typical timelines are published.

The approval path
  1. MIDASingle entry point
  2. Four checks, in parallel

    • Energy Focus GroupPower
    • SPAN and state water operatorWater
    • Local planning authorityPlanning permission
    • State data-centre committeeWhere one exists (Johor)
  3. Data Centre Task ForceDecision, co-chaired by MITI and the Digital Ministry

Our drawing of the published process.

Rule changes, 2025–2026

  1. Johor stops approving Tier 1 and Tier 2 data centres.

  2. GBI Data Centre Tool 2.0 applies to GBI-registered projects. A GBI certificate may support a MIDA application; it is not stated as required.

  3. New non-AI data-centre applications stopped nationally. No written definition of “AI data centre” had been published as of Nov 2026.

  4. Johor will not approve high-water-demand designs; only Tier 3 and 4 air-cooled halls are considered.

  5. The MITI minister told Parliament that technology transfer and unsubsidised, market-priced power will be key conditions, negotiated when investors apply. This is a stated intention, not yet a published rule.

  6. The National Economic Action Council agreed a strategic direction for sustainable data centres and a Digital Infrastructure (Data Centre) Bill, due at Cabinet in 2027.

  7. At least 30% renewable energy for the sector, with no effective date yet.

The task force received more than 40 applications in 2026. Data centres are not a standalone prescribed activity under the EIA Order 2015, though other parts of a project can trigger an environmental assessment. Take legal advice for a specific site.

Last checked 8 November 2026

Efficiency rules

These rules are national and fully public. Hall size decides which design target applies to an incentive application.

Efficiency rules
RuleWhat it saysApplies to
PUE (MITI guideline)Proposed design PUE: 1.4 for hyperscale (132 kV and above, over 21.25 MW); 1.6 for purpose-built colocation built after 2020 in that band; 1.7 for others (0.85 to under 21.25 MW)Applicants for the DESAC incentive; not an operating limit
WUE (MITI guideline)Recommended design WUE of 2.2 m³ per MWh of IT energy or lowerSame
CUE (MITI guideline)Grid factor × PUE. The guideline uses 0.758 (2021); the current Peninsular factor is 0.740 (2024, provisional)Same
DESAC incentiveNew companies: investment tax allowance of 100% (Tier 1) or 60% (Tier 2), or a special tax rate of 10% or 15%. Tier 1 needs RM1bn of capex. Applications close 31 Dec 2027Qualifying data centres
EECA 2024When served written notice: appoint a Registered Energy Manager, run an energy management system, report yearly, audit every five yearsPremises using 21,600 GJ or more (electricity and fuels) in any 12 consecutive months; Peninsular Malaysia and Labuan only

What each hall size means

Assumes 70% average IT load, the guideline’s design PUE, WUE 2.2 and the 0.740 grid factor. This is illustrative arithmetic, not a site estimate.

Size ladder for 5, 20 and 50 MW halls
IT loadDesign PUE bandIT energy / yrFacility energy / yrTimes the EECA thresholdWater at WUE 2.2CO₂e / yr
5 MW1.730,660 MWh52,122 MWh8.7×67,452 m³38,570 t
20 MW1.7122,640 MWh208,488 MWh34.7×269,808 m³154,281 t
50 MW1.4306,600 MWh429,240 MWh71.5×674,520 m³317,638 t

Any site averaging more than about 0.68 MW of total load crosses the EECA threshold, so every serious AI hall in Peninsular Malaysia is covered. Check with MITI whether a band is set by IT load or total load.

Last checked 8 November 2026

Zones, land and incentives

Investment. RM385.7bn of data-centre-related investment was approved from 2021 to H1 2026. These are approvals, not money spent. H1 2026 alone was RM95.8bn for data centres and cloud computing combined, about 44% of all approved investment. By November 2025, Johor had approved 51 projects worth RM182.96bn: 17 operating, 11 under construction and 23 not started.

Data-centre zones, cable landings and internet exchanges

Peninsular Malaysia

Zones 6–8Zones 1–59. Kulim Hi-Tech Park, approximate910. Bayan Lepas, approximate10

Klang Valley and Negeri Sembilan

TM Morib cable landing, approximateTM Morib cable landingMyIX and DE-CIX Kuala Lumpur, approximateMyIX and DE-CIX Kuala Lumpur6. Cyberjaya, approximate67. Elmina, Banting (Elmina), approximate77. Elmina, Banting (Banting), approximate78. Nilai, Port Dickson (Nilai), approximate88. Nilai, Port Dickson (Port Dickson), approximate8

South Johor

TM Sedili cable landing, approximateTM Sedili cable landingDE-CIX Johor Bahru, approximateDE-CIX Johor Bahru1. Sedenak Tech Park, approximate12. Kulai (YTL Green Data Center Park, QUANTUM Edge), approximate23. Iskandar Puteri / Nusajaya, approximate34. Johor Bahru (Nusa Cemerlang, Kempas, Tanjung Kupang) (Nusa Cemerlang), approximate44. Johor Bahru (Nusa Cemerlang, Kempas, Tanjung Kupang) (Kempas), approximate44. Johor Bahru (Nusa Cemerlang, Kempas, Tanjung Kupang) (Tanjung Kupang), approximate45. Pasir Gudang / Tebrau (Tebrau), approximate55. Pasir Gudang / Tebrau (Pasir Gudang), approximate5

Sarawak and Sabah

11. Kota Samarahan, Kota Petra, approximate11

Data-centre zone, approximateCable landing or internet exchange, approximateDistrict outlines only. No plot boundaries and no flood zones.

Data source: Department of Statistics Malaysia (district boundaries). Points placed by Croutons Research from published zone names; approximate.

Data-centre zones (the map as a table)
ZoneMapStateStatusOperators namedAnnounced capacity
Sedenak Tech Park1JohorOperating; YTL and JLand campus announced Aug 2026K2, Keppel DC, YTL“Gigawatt-scale” (no MW given)
Kulai (YTL Green Data Center Park, QUANTUM Edge)2JohorOperating and expandingYTL, Microsoft, Princeton DigitalYTL park up to 1.2 GW planned; 150 MW delivered (Jun 2026)
Iskandar Puteri / Nusajaya3JohorOperating; JS-SEZ flagship zoneDayOne, NTT, Stack, TMStack 220 MW planned; DayOne about 500 MW across Johor
Johor Bahru (Nusa Cemerlang, Kempas, Tanjung Kupang)4JohorOperating and buildingAirTrunk, Vantage, Open DC, STT GDCSTT Johor 1: 16 MW on a 120 MW campus
Pasir Gudang / Tebrau5JohorSecondary corridorRacks Central, Digital EdgeRacks Central 90 MW by end-2026; 510 MW campus planned
Cyberjaya6SelangorOperating; new AI campus to 2027AIMS, Microsoft, EdgeConneXAIMS up to 200 MW planned
Elmina, Banting7SelangorUnder construction; land soldSime Darby Property, BridgeNot stated
Nilai, Port Dickson8Negeri SembilanUnder construction; land acquiredVena Nexus, Gamuda, TeraVena Nexus 350–450 MW (sources differ)
Kulim Hi-Tech Park9KedahPlanned; 350 MW gas plant on siteMaxland DataNot stated
Bayan Lepas10PenangOperatingOpen DC30 MW
Kota Samarahan, Kota Petra11SarawakAnnounced 2023 and laterFutureData; Zecon with Sarawak Energy200 MW (2023 announcement)

Johor capacity, two counts

Johor capacity, two counts
SourceOperationalUnder constructionPlanned
JLL, Apr 2026850 MW1,800 MW2,700 MW
Cushman & Wakefield, H1 20261,110 MW602 MW2,486 MW
Published land deals, price per sq ft
Port Dickson, Negeri SembilanSep 2026105 RM psf
Tanjung Kupang, JohorJun 2026142 RM psf
QUANTUM Edge, Kulai, JohorApr 2026130 RM psf
Banting, SelangorFeb 2026125 RM psf
Nusa Cemerlang, Johor BahruDec 2024150 RM psf
East Ledang, Iskandar PuteriJun 2024115 RM psf

Price per sq ft derived from published area and price. Deals from 2024 to 2026. Download the deals as CSV, free to reuse with credit (CC BY 4.0).

Published land deals
DateLocationBuyerAreaPriceRM psf
Sep 2026Port Dickson, Negeri SembilanTera Data Centers221.67 acresRM1.013bn105
Jun 2026Tanjung Kupang, JohorDayOne (conditional; completion expected H2 2027)about 64 acresRM398.1m142
Apr 2026QUANTUM Edge, Kulai, JohorHyperscale operator (conditional)49.6 acresRM280.8m130
Feb 2026Banting, SelangorBridge Data Centres136 acresRM740.7m125
Dec 2024Nusa Cemerlang, Johor BahruData Cloud Innovation18.4 acresRM120.1m150
Jun 2024East Ledang, Iskandar PuteriUnnamed global operator28.9 acresRM144.9m115

Incentives. DESAC (see Efficiency rules) is the incentive built for data centres. The JS-SEZ 5% rate covers AI and quantum supply-chain manufacturing and other sectors, not data centres. Forest City’s 5% rate covers fintech and financial services, not data centres.

Last checked 8 November 2026

Physical risk and connectivity

Flood losses and events are public by state. JPS flood hazard maps are not public, so check flood risk site by site.

  • 2025 flood losses were RM636.9m nationally (RM933.4m in 2024), including Johor RM72.1m and Selangor RM52.9m. The December 2021 to January 2022 floods cost RM6.1bn.
  • At 8 am on 21 March 2025, 10,763 people were in relief centres in Johor, including 4,291 in Johor Bahru and 1,152 in Kulai.
  • NAHRIM projects 0.67–0.71 m of sea level rise by 2100 for Peninsular Malaysia. Under its high-emissions scenario, coastal flooded area grows 76.9%. Johor’s low-lying west coast is exposed.
  • 2024 was Malaysia’s fourth-warmest year since 1981 (27.55°C mean). With humidity near 80%, halls need mechanical cooling all year.
  • TM’s Sedili station in Johor hosts the Asia Link Cable and will land CANDLE (2028). TM’s Morib station in Selangor is built for up to three systems, including SEA-ME-WE 6.
  • KL to Singapore is about 8 ms (8.39 ms average, 8 Nov 2026). Johor to Singapore under 3 ms is a vendor claim.
  • MyIX has 118 members and peaked at 2.6 Tbps in 2024. DE-CIX runs exchanges in KL and Johor Bahru.

Heat and rainfall by data-centre district, 2016–2025, are in our climate research.

Flood losses
Malaysia, 2024933.4 RM m
Malaysia, 2025636.9 RM m
Johor, 202572.1 RM m
Selangor, 202552.9 RM m

Data source: Department of Statistics Malaysia. Losses in RM million.

Cable landing stations and internet exchanges are on the zones map.

Last checked 8 November 2026

What this guide does not know

The guide never claims to know any of the following. Each one can only be confirmed for a specific site:

  • Spare grid capacity by substation (confirmed by TNB, site by site)
  • Flood hazard zones (request JPS data for the site)
  • Water allocation per site
  • Approval timelines (none published)
  • Whether a given project counts as “AI” after February 2026
  • Land prices beyond the six published deals

Last checked 8 November 2026

After it’s built: energy per answer

The Croutons mascot, a chrome robot cat

Once a hall is running, the efficiency rules above measure the building. They do not measure the work done inside it. Croutons measures energy, water and carbon per AI answer and reports them in the same MITI and EECA terms, so an operator can show more answers per megawatt.

What a megawatt is worth in Johor

One megawatt of facility power, for one year. Estimates.

In a hall where power is the limit, one megawatt’s electricity costs about RM4.4 million a year, while the GPU time it runs sells for about RM50–167 million. The answers a capped megawatt can’t serve are worth roughly 10 to 40 times its electricity bill.

Per MW, per yearValueWorked out as
ElectricityRM4.4m8,760 MWh at RM0.50/kWh
GPU time, 30% of list priceRM50mAbout 2.4m GPU-hours at about RM21
GPU time, full list priceRM167mAbout 2.4m GPU-hours at about RM69

Assumptions: 1 MW of facility power at PUE 1.4 leaves about 714 kW for IT, enough for about 397 NVIDIA GB200 GPUs at 1.8 kW each at the wall (our estimate, including a share of host and switching). GPUs busy 70% of hours. Electricity at RM0.50/kWh, rounded from the ultra-high-voltage tariff (47.09–51.18 sen/kWh from 1 Jul 2025, before fuel surcharge), with the full megawatt drawn all year, which overstates the bill. GPU time priced from 30% of the Malaysian GB200 list price (Nov 2026) up to full list, about RM21–69 per GPU-hour; large customers pay less than list. Croutons, November 2026.

Last checked 8 November 2026

Looking at a specific site?

We prepare a site feasibility brief that checks power, water, approval and flood questions against the public record and lists what has to be confirmed with TNB, the state and JPS.

FAQ

Questions

Can you still build a non-AI data centre in Malaysia?

Not under a new application. Since 24 February 2026, new non-AI data-centre applications have been stopped nationally. No written definition of "AI data centre" had been published as of November 2026.

What PUE does Malaysia require for data centres?

MITI’s guideline sets proposed design targets for DESAC incentive applicants: 1.4 for hyperscale, 1.6 for newer colocation, and 1.7 for others. They are not operating limits.

Does EECA 2024 apply to data centres?

Yes, in Peninsular Malaysia and Labuan, for any premises using 21,600 GJ or more in any 12 consecutive months, once the Energy Commission serves written notice. That threshold is about 0.68 MW of average load.

How much water do data centres get in Johor?

In 2024 Johor granted 21% of the volume data centres requested. The state also caps WUE at 1.8 and no longer approves Tier 1 and 2 halls.

What does data-centre land cost in Malaysia?

Six published deals from 2024 to 2026 work out to about RM105–150 per sq ft.