Malaysia data-centre research

The public data behind our guide to building AI data centres in Malaysia: ten years of hourly weather for 11 data-centre districts, the figures that conflict and which ones to use, what is not public, and the full terms of the DESAC incentive and EECA 2024.

Contents

Climate and cooling, 2016–2025

Malaysia is not too hot for dry cooling. Across 11 data-centre districts, outside air passed 32°C for only 13–142 hours a year from 2016 to 2025, under 2% of the time, and the hottest hour in ten years was 33.8–36.1°C. Rain is frequent: the longest dry spell was 7–17 days, and the driest 60 days still brought 63–165 mm.

Hours a year above 32°C, by district
Nilai142 h/yr
Kulim138 h/yr
Cyberjaya112 h/yr
Kota Samarahan109 h/yr
Pasir Gudang63 h/yr
Iskandar Puteri48 h/yr
Port Dickson47 h/yr
Banting34 h/yr
Kulai / Sedenak33 h/yr
Bayan Lepas18 h/yr
Pengerang13 h/yr

Average of 2016–2025. Hourly ERA5 reanalysis via Open-Meteo (Copernicus). Analysis: Croutons Research, November 2026.

Climate by data-centre district, 2016–2025
DistrictStateHours/yr above 30°CHours/yr above 32°CHottest hourRain, average / driest yearRain in driest 60 days
Kulai / SedenakJohor4433335.5°C3,008 / 2,249 mm150 mm
Iskandar PuteriJohor5164835.8°C2,873 / 2,354 mm135 mm
Pasir GudangJohor6336336.0°C3,274 / 2,578 mm136 mm
PengerangJohor2461334.2°C2,600 / 1,962 mm63 mm
CyberjayaSelangor83411235.7°C3,308 / 2,439 mm124 mm
BantingSelangor6773433.8°C3,592 / 2,621 mm117 mm
NilaiNegeri Sembilan91014236.0°C3,110 / 2,390 mm123 mm
Port DicksonNegeri Sembilan6184735.0°C3,013 / 2,161 mm119 mm
KulimKedah87213836.1°C3,822 / 2,127 mm70 mm
Bayan LepasPenang3121834.5°C3,533 / 2,207 mm115 mm
Kota SamarahanSarawak73010935.2°C4,043 / 2,823 mm165 mm

Download the table as CSV, free to reuse with credit (CC BY 4.0). Weather data by Open-Meteo.com.

What it means for cooling

  • The cooling-water temperature a hall is designed for decides its water use more than its location does. With warm-water liquid cooling at 40°C or more and dry coolers running about 6°C above outside air, heat can go to outside air whenever it is below about 34°C. Every district’s hottest hour in ten years was 33.8–36.1°C.
  • Evaporative water is then needed only for peak hours. Our estimate for a 20 MW hall is about 4,500 m³ a year of top-up for about 150 peak hours, against about 44,000 m³ of rain a year on a 2-hectare roof in a dry year (about 2,200 mm).
  • Coastal sites have the mildest peaks: Pengerang (13 hours a year above 32°C), Bayan Lepas (18) and Banting (34, with the lowest ten-year peak, 33.8°C). The inland belt runs hottest: Nilai (142), Kulim (138) and Cyberjaya (112).
  • Pengerang is the mildest and also the driest district in the set, with 1,962 mm in its driest year.

Caveats. ERA5 is a 9–25 km grid that smooths peaks, so real peaks, especially in urban Cyberjaya, run hotter. Treat the hour counts as lower bounds and use MetMalaysia station data or ASHRAE design conditions for engineering. ERA5 rainfall can read high against rain gauges. The water figures are our engineering estimates, not measurements.

Last checked 8 November 2026

Figures that conflict, and which we use

Several Malaysian data-centre figures circulate in two versions. These are the ones we use, and why.

Conflicting figures
FigureVersions in circulationWhat we use
Operating data centres, Peninsular45 centres on 6.04 GW (Aug 2026), or 57 centres needing 6,237 MWBoth are official; they differ by scope. Quote the scope and date with either.
Approved data-centre water, 2025–2030445.04 MLD (Oct 2026), or 514 MLD (Nov 2025 projection)Use 445.04 MLD. The 514 MLD projection is superseded.
2030 data-centre peak demand8.39 GW, or 12.9 GWUse the ministry’s 8.39 GW. We found no traceable source for 12.9 GW.
YTL Green Data Center Park, KulaiUp to 1.2 GW planned (Aug 2026), or 500 MW (original billing)Use the newer figure and say it is planned; 150 MW was delivered by Jun 2026.
Vena Nexus, Negeri Sembilan350 MW (w.media, Jun 2026), or 450 MW (RHB, Oct 2026)Neither says whether it is a phase or full build-out. Show both.
Johor capacityJLL (Apr 2026): 850 MW operational. Cushman & Wakefield (H1 2026): 1,110 MW operationalBroker counts differ by method. Show both, named.
Sea level rise by 2100NAHRIM: 0.67–0.71 m for Peninsular Malaysia. A 2012 PLANMalaysia dashboard: 2.66 m at Kukup, JohorUse NAHRIM.
Grid emission factor0.758 kg CO₂e/kWh (2021, used in the MITI guideline), or 0.740 (2024, provisional)Use 0.740 for current estimates and say the guideline uses 0.758.
National Data Centre FrameworkPromised for October 2025We found no record that it was issued. The current track is the October 2026 strategic direction and a Data Centre Bill due at Cabinet in 2027.

Last checked 8 November 2026

What is not public

These are the facts an investor most wants and the public record does not hold. Anything claiming to know them for a site should say where the data came from.

What is not public
Not publicWhy it mattersWhere it comes from
Spare grid capacity by substation; a TNB grid mapThe biggest siting factorConfirmed by TNB, site by site
JPS flood hazard mapsSite-level flood riskRequest JPS data for the site
Water allocation per siteApproval riskGranted per application by the state
Water reserve margins for Penang, Negeri Sembilan and KedahSupply risk outside Johor and SelangorNot published
Approval timelinesInvestment planningNo service standard is published
A written definition of “AI data centre”Whether a project qualifies after 24 Feb 2026None published as of Nov 2026
Official MW capacity by state; park boundariesMarket sizing and mappingOnly broker counts and announcements
Terrestrial fibre routes; an independent Johor–Singapore latency figureConnectivity claimsUnder 3 ms is a vendor claim

Last checked 8 November 2026

DESAC and EECA in full

DESAC incentive

DESAC incentive terms
TermWhat it says
WhoQualifying data centres, new and existing companies
New companiesInvestment tax allowance of 100% (Tier 1) or 60% (Tier 2) of qualifying capex, against up to 100% of statutory income, for 5 or 10 years. Or a special tax rate of 10% (Tier 1) or 15% (Tier 2) instead, excluding IP income
Existing companiesInvestment tax allowance of 60% or 30%, against up to 70% of statutory income, for 5 years
Tier 1 thresholdRM1bn of capex (existing companies: RM300m over 5 years)
ConditionsRM2.5m paid-up capital; at least 50% Malaysian staff earning RM5,000 or more a month; at least one green technology; at least two local vendor programmes; Industry 4.0 elements
Application window1 Jan 2022 to 31 Dec 2027, before the first sales invoice
Efficiency targetsMITI’s proposed design PUE (1.4, 1.6 or 1.7 by size and type) and recommended design WUE of 2.2 m³/MWh apply to applicants. They are not operating limits

Source: MIDA DESAC guideline; MITI Guidelines for Sustainable Development of Data Centres.

EECA 2024 (Act 861)

EECA 2024 duties
TermWhat it says
Threshold21,600 GJ or more of electricity and fuels together in any 12 consecutive months (6,000 MWh, about 0.68 MW of average load)
WherePeninsular Malaysia and Labuan; not Sabah or Sarawak
In force1 January 2025. Duties start when the Energy Commission serves written notice
Registered Energy ManagerAppointed within 3 months of the notice
Energy management systemWithin 1 year of that appointment
ReportingA yearly report within 30 days after each year
Energy auditFirst within 1 year of the notice, then every fifth year

Source: Energy Commission; Efficient Energy Management Regulations 2024 (P.U.(A) 466/2024). Not confirmed: when the first notices were served.

Last checked 8 November 2026

Other findings

Other findings
TopicFindingSource
Renewable energy ruleAt least 30% renewable energy for the sector, approved Oct 2026. No effective date; not yet settled whether it is measured on capacity or consumption. Under CRESS, providers pay 14 sen/kWh and users a separate 4 sen/kWhMalay Mail; w.media
New water supplyRanhill SAJ estimates Johor needs about 1,000 MLD more by 2030 for all users, not data centres alone. Selangor is studying a 300 MLD desalination plantThe Star
Reclaimed water in JohorIndah Water supplies 12 MLD of treated effluent to the Gelang Patah plant and 4 MLD to Ulu Tiram. A national reclamation policy is still being studiedThe Star; theSun; Malay Mail
JS-SEZ 5% tax rateCovers manufacturing in the AI and quantum supply chain, among other sectors, for 15 years above RM1bn of new investment or 10 years for RM500m to RM1bn. Data centres are not listedMIDA JS-SEZ snapshot
Forest City 5% tax rateCovers fintech, financial business services and foreign payment operators, with 0% for single family offices. Data centres are not eligibleSkrine; Malay Mail
Environmental assessmentData centres are not a standalone prescribed activity under the EIA Order 2015, though other parts of a project can trigger an EIALegal commentary (Rajah & Tann)
Neighbour objectionsThe 21-day objection window is a general planning-law rule (Town and Country Planning Act s21(6)), not a data-centre rulePlanning law

Last checked 8 November 2026

Public data and how it can be used

Which public datasets can be used to map Malaysian data-centre sites, and on what terms.

Public data and licences
DataPublisherDetailCan it be used in maps?
District boundariesDOSMDistrictYes, credited “Data source: Department of Statistics Malaysia”
Flood losses by stateDOSMStateYes, with the same credit
Live flood stations (InfoBanjir)JPSStationLink only; no licence or export
Flood hazard mapsJPS—Not public
Sea level and flood projections to 2100NAHRIMRegionFigures in text
Power lines and substationsOpenStreetMapFeatureYes, under ODbL, credited “© OpenStreetMap contributors”
Submarine cable routesTeleGeographyRouteCredited screenshots only; tracing routes needs a paid licence
Landing stationsTM releasesSiteYes, as points placed from the releases
Internet exchangesInternet Society PulseCityYes, as city points
Hourly weather (ERA5 reanalysis)Open-Meteo, Copernicus9–25 km gridYes, under CC BY 4.0, credited to Open-Meteo
GADM boundaries; JUPEM base mapsGADM; JUPEM—No: GADM needs permission for commercial use; JUPEM is paid

Last checked 8 November 2026