Malaysia data-centre rules tracker: every change, dated

Every rule change, newest first, with its status and source. Last updated 10 November 2026.

Contents

There is no general moratorium on data centres in Malaysia. Since 24 February 2026, new applications for non-AI data centres have been stopped nationally (Malay Mail); AI data centres can still apply, although no written definition of “AI data centre” has been published.

In 2026 Malaysia also announced a 30% renewable-energy requirement with no effective date (Malay Mail), charges for unused power allocations with no published rate (The Star), and a Digital Infrastructure (Data Centre) Bill due at Cabinet in 2027, whose text is not public (Malay Mail). Johor’s water rules are in force.

24 Feb 2026
New non-AI applications stopped (Malay Mail)
2027
Data Centre Bill due at Cabinet (Malay Mail)
30%
Renewable-energy floor announced, no effective date (Malay Mail)

What data-centre rules has Malaysia introduced?

Newest first. In force: applies now. Announced: stated by a minister or agency, with no published rule or rate. Proposed: being drafted. RSS feed · Get monthly updates by email.

Malaysia data-centre rule changes, newest first
DateRuleWhoStatusSource
Grid access released in phases under binding Electricity Supply Agreements; operators submit 10-year staggered load projections. No financial penalty specified.Ministry of Energy Transition (written reply)In force(Malay Mail)
At least 30% renewable energy for the data-centre sector. No effective date given.Federal governmentAnnounced(Malay Mail)
Connected Load Charge “increased” to deter over-applying for capacity. New rate and start date not stated.Deputy Prime Minister (written reply)Announced(The Star)
Strategic direction for sustainable data centres agreed; a Digital Infrastructure (Data Centre) Bill to go to Cabinet in 2027. The bill’s text is not public.National Economic Action Council; Ministry of DigitalProposed(Malay Mail)
Operators charged for allocated capacity whether used or not. No rate or effective date.MITI minister, Dewan RakyatAnnounced(The Star)
Technology transfer and unsubsidised, market-priced power to be key conditions, negotiated when investors apply.MITI minister, Dewan RakyatAnnounced(The Vibes)
Operators that over-reserve power or water “will be penalised”. No rate published.Deputy Prime Minister, ParliamentAnnounced(w.media)
Johor will not approve high-water-demand designs; only Tier 3 and Tier 4 air-cooled halls considered.Johor state governmentIn force(Malay Mail)
New non-AI data-centre applications stopped nationally. No written definition of “AI data centre” published.Prime MinisterIn force(Malay Mail)
GBI Data Centre Tool 2.0 applies to GBI-registered projects.Green Building IndexIn force(Baker McKenzie)
Johor stops approving Tier 1 and Tier 2 data centres.Johor state governmentIn force(NST via w.media)
Johor data-centre water tariff of RM5.33 per m³.Johor state governmentIn force(The Star)
HV Ultra time-of-use electricity tariff for data centres: 55.18 sen/kWh peak, 51.09 off-peak, plus capacity and network charges.Energy Commission; TNBIn force(Energy Commission)

Is there a data-centre moratorium in Malaysia?

No general one. Only new non-AI data-centre applications are frozen, since 24 February 2026 (Malay Mail). Johor separately does not approve Tier 1 or Tier 2 halls (NST via w.media) or high-water-demand designs (Malay Mail). See what counts as an AI data centre.

What is the Digital Infrastructure (Data Centre) Bill?

A proposed law, not yet tabled. The National Economic Action Council agreed a strategic direction for sustainable data centres on 19 October 2026, and the bill is due to go to Cabinet in 2027 (Malay Mail). Its text has not been published, so any description of what it requires is unconfirmed.

What is not public

We could not confirm these from a published source as of 10 November 2026. Do not assume them:

  • The text of the Data Centre Bill
  • A written definition of “AI data centre”
  • Rates for unused-capacity charges
  • The effective date of the 30% renewable-energy rule

Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.

Sources

Last checked 10 November 2026

Questions

Is there a data-centre moratorium in Malaysia?

No general moratorium. Only new non-AI data-centre applications have been stopped, since 24 February 2026.

When will the Data Centre Bill be passed?

It is due at Cabinet in 2027. Its text has not been published.