PUE, WUE and CUE in Malaysia: what the MITI guideline requires, and what it doesn’t

What the guideline sets, who it binds, and the arithmetic for 5, 20 and 50 MW halls.

Contents

MITI’s guideline sets proposed design PUE targets for data centres applying for the DESAC incentive: 1.4 for hyperscale (132 kV and above, over 21.25 MW), 1.6 for purpose-built colocation built after 2020, and 1.7 for others from 0.85 to under 21.25 MW (MITI). They are design targets for incentive applicants, not operating limits or general law.

The guideline recommends a design WUE of 2.2 m³ per MWh and computes CUE with the 2021 grid factor of 0.758 (MITI); the current Peninsular factor is 0.740 (2024 provisional) (Energy Commission). Johor separately allows a WUE of 1.8, unit not published (w.media).

1.4 PUE
Hyperscale design target (MITI)
1.7 PUE
Target for other data centres, 0.85 to under 21.25 MW (MITI)
2.2 m³/MWh
Recommended design WUE (MITI)

What PUE does MITI’s guideline require, and is it mandatory?

MITI proposed design PUE targets
CategorySizeDesign PUE target
Hyperscale132 kV and above, over 21.25 MW1.4
Purpose-built colocationBuilt after 20201.6
Others0.85 to under 21.25 MW1.7

Source: MITI guideline.

Not as a general law. The targets are proposed design values for DESAC incentive applicants (MITI) (MIDA). A data centre that does not apply for DESAC is not bound by them, although EECA 2024 separately requires large energy users to report and manage energy (see EECA 2024). Check with MITI whether a size band is set by IT load or total load.

What is PUE, and how is it calculated?

Power usage effectiveness is total facility energy divided by IT equipment energy. A PUE of 1.7 means 0.7 kWh of cooling and other overhead for every kWh the servers use. Worked example for a 20 MW hall at 70% load: IT energy 122,640 MWh a year; facility energy 208,488 MWh; PUE = 208,488 ÷ 122,640 = 1.7.

What are WUE and CUE?

WUE is site water used divided by IT energy. MITI recommends 2.2 m³/MWh at design, the same number as 2.2 L/kWh; actual WUE is disclosed yearly (MITI). CUE is carbon per unit of IT energy: grid emission factor × PUE.

CUE on two grid factors, kg CO₂e per kWh of IT energy
PUECUE at 0.758 (guideline, 2021)CUE at 0.740 (2024 provisional)
1.41.0611.036
1.61.2131.184
1.71.2891.258

Factors: MITI guideline (0.758); Energy Commission (0.740). Peninsular grid.

How do Johor’s rules interact with MITI’s guideline?

They stack. MITI’s values are national design targets for incentive applicants; Johor’s are state conditions on water approval. Johor allows a WUE of 1.8 (w.media), stricter than MITI’s 2.2 if it is in the same unit, and since 10 March 2026 considers only Tier 3 and Tier 4 air-cooled designs (Malay Mail). More on the water page.

What do the targets mean for 5, 20 and 50 MW halls?

Size ladder at 70% load
IT loadDesign PUE bandIT energy / yrFacility energy / yrWater at WUE 2.2CO₂e / yr
5 MW1.730,660 MWh52,122 MWh67,452 m³38,570 t
20 MW1.7122,640 MWh208,488 MWh269,808 m³154,281 t
50 MW1.4306,600 MWh429,240 MWh674,520 m³317,638 t

70% average load; CO₂e at 0.740 kg/kWh on facility energy. The 20 MW hall sits in the 1.7 band because it is under 21.25 MW.

What can’t PUE show?

PUE measures overhead, not output. Two halls with the same PUE can produce very different amounts of AI work per MWh, depending on load and workload mix. Our method paper proposes adding answers or tokens per MWh as the production variable, so output per allocated megawatt can be measured.

What is not public

We could not confirm these from a published source as of 10 November 2026. Do not assume them:

  • Measured PUE or WUE for named Malaysian sites
  • Whether MITI’s size bands use IT load or total load
  • The unit of Johor’s WUE 1.8

Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.

Sources

Last checked 10 November 2026

Questions

Is MITI’s PUE target mandatory?

No. The 1.4, 1.6 and 1.7 targets are proposed design values for DESAC incentive applicants, not operating limits or general law.

What WUE does MITI recommend?

2.2 m³ per MWh of IT energy at design, the same number as 2.2 L/kWh.