Investing in Malaysian data centres: capacity, money, contracts, costs and risks

Every figure dated and sourced, with what each one counts. No forecasts of our own and no stock views.

Contents

Johor had 1,110 MW of operating data-centre IT capacity in H1 2026, 602 MW under construction and colocation vacancy of 0.7% (Cushman & Wakefield via EdgeProp, 27 Aug 2026). Nationally, data centres drew 1,374 MW against 2,346 MW contracted in August 2026 (The Star), and TNB has signed supply for 61 projects with 8.35 GW of maximum demand (MBSB via TNB).

Google committed US$15bn for 2027–2028 on 4 November 2026 (Google), on top of AWS’s US$6.2bn (MIDA), Oracle’s US$6.5bn (MIDA) and Microsoft’s US$2.2bn (Microsoft). MIDA approved RM385.7bn of data-centre-related investment from 2021 to H1 2026; these are approvals, not money spent (MIDA).

1,110 MW
Johor operating IT capacity, H1 2026 (C&W)
0.7%
Johor colocation vacancy (C&W)
58.6%
Contracted power actually used, Aug 2026 (Malay Mail)
US$15bn
Google’s 4 Nov 2026 commitment (Google)
RM375.8 /kW/month
Electricity per kW of maximum demand, HV Ultra, 80% load (calculated below)

How much data-centre capacity does Malaysia have?

Depends on who counts and what. The consultancies measure IT load; the government measures grid demand. They should not be added together.

Capacity counts and what each measures
SourceOperatingUnder constructionPipelineScope and date
Cushman & Wakefield (EdgeProp)1,110 MW602 MW2,486 MW plannedJohor, IT load, H1 2026
Knight Frank (EdgeProp)1,110 MWNot given8,542 MWJohor, IT load; pipeline scope not defined; Atlas 2026
JLL (The Edge)850 MW completed1,800 MW2,700 MWJohor Bahru, 2Q 2026, basis not stated
Knight Frank (Malay Mail)504.8 MW1,313 MW upcomingNot givenMalaysia, IT load, Dec 2024
Grid demand: used against reserved
As ofActual drawCompared withShareSource
Jun 2025603 MW1,276 MW declared maximum demandAbout 47%(w.media)
Apr 20261,102 MW2,050 MW maximum approved demandAbout 54%(EdgeProp)
Aug 20261,374 MW2,346 MW contracted58.5–58.6%(The Star) (Malay Mail)

The comparison base changes each time (declared, approved, contracted), so the three shares are not a like-for-like trend.

TNB’s pipeline is larger again: 61 projects with 8.35 GW of maximum demand under supply agreements, 42 of them (5.65 GW) connected, with actual data-centre load of 1.26 GW in June 2026 (MBSB via TNB). Data centres were about 6% of TNB’s electricity sales (MBSB via TNB); 68% of secured capacity is in Johor (The Star).

Which campuses are being built, and how big?

Thirty campuses with the operator’s announced megawatts, whether that figure is IT load or total power, status and source. Where the source does not say, we say “not stated”.

Malaysian data-centre campuses
OperatorCampusStateAnnounced MWMW basisStatusSource
YTL PowerYTL Green Data Center Park, KulaiJohor1,200 planned (raised from 600); 298 contractedNot statedOperating; 200 MW more under construction (Jun 2026)25 Jun 2026
AirTrunkJHB1 and JHB2, Johor Bahru and Iskandar PuteriJohorOver 420 combinedIT loadJHB1 operating since Jul 2024; JHB1 and JHB2 almost fully contracted (Apr 2026)30 Apr 2026
AirTrunkJHB3 and JHB4, Iskandar PuteriJohor280 combinedIT loadPlanned (Apr 2026)30 Apr 2026
DayOneNusajaya and Kempas Tech ParksJohor390 in service, or over 478 operational (same company page)Not statedOperatingRead 10 Nov 2026
Princeton Digital GroupJH1, Sedenak Tech ParkJohor200 (raised from 150)Not statedPhase 1 (52 MW) delivered Jul 2024; buildings 3 and 4 under construction (Dec 2025)17 Dec 2025
STT GDCSTT Johor, Nusa CemerlangJohorUp to 166 (raised from 120)IT loadUnder construction; Johor 1 (16 MW) due end-202624 Feb 2025
Vantage Data CentersJHB1, Sedenak Tech ParkJohorOver 300 across 3 buildings at full buildIT loadAcquired from Yondr (Nov 2025)24 Nov 2025
Bridge Data CentresMY06, Sedenak Tech Park (ByteDance)Johor110 across 3 buildingsNot statedPhase 1 opened Oct 202220 Oct 2022
K2 StrategicJHR1, Sedenak Tech ParkJohor300Gross powerTNB supply agreement signed (Sep 2023); later status not published15 Sep 2023
Racks CentralAIDC campus, Pasir GudangJohor510 campus; phase 1 70Not statedUnder construction; phase 1 due 1Q 202730 Jun 2026
TM NxeraIskandar Puteri campusJohorOver 200; 280 supply secured280 = grid supplyUnder construction; phase 1 (64 MW) from Sep 202612 Jan 2026
NTT DATAJHB10, Gelang PatahJohorAbout 290; first building 48IT loadPlanned; first building Apr 20276 Dec 2024
Bitdeer AIA201 and A202, Johor BahruJohor86.8Not statedEnergisation 1Q and 3Q 202714 Oct 2026
EdgeConneXJohorJohor36, up to 160Not statedNot statedRead 10 Nov 2026
Open DCJB1, Johor BahruJohor20Not statedOperating since 201523 Sep 2026
GoogleElmina Business ParkSelangorNot disclosedn/aOperating (Nov 2026)4 Nov 2026
GoogleNew campuses, Selangor and Negeri SembilanSelangor; Negeri SembilanNot disclosedn/aPlanned, 2027–20284 Nov 2026
AIMS (TIME dotCom joint venture)New AI data centre, CyberjayaSelangorUp to 200, subject to engineeringNot statedLand acquired; completion targeted 20276 Feb 2026
Digital RealtyKUL10, KUL11 and a future site, CyberjayaSelangorAbout 32IT loadKUL10 and KUL11 operating; future site mid-20288 Jun 2026
NTT DATACyberjaya campus (CBJ1–CBJ6)SelangorCBJ5 and CBJ6: 22Facility loadOperating10 Oct 2023
Bitdeer AIA101–A103, CyberjayaSelangorAbout 71.5Not statedA103 energisation 1Q 202814 Oct 2026
MicrosoftMalaysia West region (3 availability zones)Greater Kuala LumpurNot disclosedn/aOperating since 28 May 202528 May 2025
AWSAsia Pacific (Malaysia) region (3 availability zones)Not disclosedNot disclosedn/aOperating since Aug 202421 Aug 2024
Google affiliate (Pearl Computing); Gamuda buildsPort Dickson campus, 389 acresNegeri Sembilan500–1,000 planned at land saleNot statedUnder construction; Gamuda contracts to 20281 Sep 2026
Vena NexusNexus Yang, SenawangNegeri SembilanAbout 350 initialIT loadGround broken (Mar 2026)3 Mar 2026
Open DCPE2, Bayan LepasPenang30, target 100Not statedAbout 15 MW energised (Sep 2026)23 Sep 2026
Privasia (Silverstreams)Bagan DatukPerakPhase 1 10.06Not statedUnder construction; go-live end-2027 or early 202810 Apr 2026
Victoria Data CentreJasinMelakaAbout 100 (also given as up to 96)Not statedIntention announced (Feb 2026)5 Feb 2026
FutureDataFutureData Park, Kota SamarahanSarawak200 (2023), later 500 (2024)Not statedPlanned; no 2026 update published9 Oct 2024
FirmusTwo AI Factory sites (OpenAI anchor)Not disclosedNot disclosedn/aStatus not stated (Sep 2026)8 Sep 2026

Download the ledger as CSV, free to reuse with credit (CC BY 4.0). Announced MW is the operator’s figure, often full build-out, and is not additive across rows.

How much have the big technology companies committed?

Technology company commitments
CompanyAmountPeriodWhereTypeSource
GoogleUS$15bn2027–2028New campuses in Selangor and Negeri SembilanCommitment (4 Nov 2026)(Google)
GoogleUS$2bnNot statedElmina, Selangor; cloud regionCommitment (30 May 2024); operating(Google)
OracleMore than US$6.5bnNot statedMalaysia, site not namedCommitment (2 Oct 2024)(MIDA)
AWSAbout US$6.2bnThrough 2038Malaysia region, 3 zonesCommitment; region open since Aug 2024(MIDA)
MicrosoftUS$2.2bn4 years from May 2024Malaysia West (Greater KL); Johor Bahru region plannedCommitment; region live 28 May 2025(Microsoft) (Microsoft)
ByteDanceAbout RM10bnNot statedMalaysia; RM1.5bn more at SedenakProposal cited by a minister (Jun 2024)(MIDA)
YTL Power with NvidiaNot stated by YTLFrom 2024Kulai, Johor; 500 MWCommitment (8 Dec 2023)(YTL Power)
Alibaba CloudNo Malaysia amountNot givenSecond region, JohorOpened 9 Jun 2026(Bernama)
Tencent CloudNo amountNo dateJohorPlanned (18 Aug 2026)(Tencent)
OpenAI via FirmusNot disclosedMulti-yearTwo Malaysian sitesCompute contract (8 Sep 2026)(Firmus)

The US$15bn, US$6.5bn, US$6.2bn and US$2.2bn commitments total US$29.9bn, or US$31.9bn with Google’s 2024 US$2bn. They cover cloud regions, skills and energy as well as buildings, and are pledges, not spending to date. Google’s “more than 1 GW” in the 2026 announcement is new clean-energy generation for the grid, not data-centre capacity (Google).

How much data-centre investment has Malaysia approved?

Approved investment and what each figure counts
FigureWhat it countsSource
RM385.7bnData-centre-related investment approved, 2021 to H1 2026(MIDA, 14 Sep 2026)
RM95.8bnData-centre and cloud projects approved in H1 2026, close to 44% of all approvals(MIDA, 28 Aug 2026)
RM34.6bn, 33 projectsData centres and cloud computing, Q1 2026(MIDA)
143 projects, RM144.4bnData-centre projects approved, 2021 to Jun 2025(The Star (Dewan Rakyat))
27 projects, RM225.97bnApproved by the Data Centre Task Force to Jul 2026: Johor 16, Selangor 10, Negeri Sembilan 1(The Star (written reply))

The series use different definitions; do not subtract one from another to get annual figures. MIDA gives 2025’s total approvals for all sectors as RM426.7bn in one release and RM431.1bn in a later one (MIDA).

Which Bursa-listed companies earn from data centres?

Contractors, landowners, power-equipment firms and a few owners. Most do not report data-centre revenue separately, so contract awards are the visible exposure, and an award is not revenue already earned.

Bursa-listed data-centre contracts and land deals, 2026
DateCompanyRoleContract or dealRMSource
5 Nov 2026Sunway ConstructionMain contractorHyperscale data centre, Bandar Serendah, Selangor (client not disclosed)1.74bn(The Edge)
4 Nov 2026Sunway ConstructionMEP contractorAdditional MEP fit-out, Johor data centre; lifts that project to RM2.51bn920.8m(The Star)
13 Oct 2026MN HoldingsSubstationTwo 275kV consumer landing stations for a data centre, central region293.88m(The Star)
3 Sep 2026Kerjaya ProspekMEP contractorMEP fit-out, data centre at Iskandar Puteri858m(The Star)
28 Aug 2026GamudaMain contractorTwo hyperscale data centres, Port Dickson (US technology client, not named)3.57bn(EdgeProp)
20 Aug 2026Mah SingLand seller78.8 acres at Southville City, Sepang, at RM180 psf617.9m(The Star)
5 Aug 2026GamudaMain contractorHyperscale data centre, Port Dickson1.71bn(The Star)
3 Aug 2026Sunway ConstructionMEP contractorMEP fit-out, Johor data centre (US technology client)1.02bn(BusinessToday)
27 Jul 2026SNS Network TechnologyServer supplierAI servers for a data centre in Malaysia (US$298.66m)About 1.22bn(The Star)
1 Jul 2026BinastraDesign and buildPhase 2, Cheras data centre491.2m(The Star)
23 Jun 2026Paragon GlobeLand sellerAbout 65 acres, Tanjung Kupang, to a DayOne unit398.1m(The Star)
17 Jun 2026Sunway ConstructionSubstationChange orders for substations at two Johor data centres; total RM865.6m664.4m(The Star)
17 Apr 2026Sunway ConstructionMain contractorHyperscale data centre, Bandar Serendah, Selangor1.75bn(EdgeProp)
17 Apr 2026GamudaMain contractorHyperscale data centre, Port Dickson1.72bn(Malay Mail)
13 Apr 2026MitrajayaMain contractorEarly works, NEXTDC KL1 stage 4 (main works now RM844.66m)54m(The Star)
9 Apr 2026CrescendoLand seller49.72 acres, Kota Tinggi, to Digital Edge346.53m(The Star)
1 Apr 2026IJMMain contractorPackage 2 core and shell, Elmina Business Park (for Sime Darby Property)658.01m(The Star)
25 Mar 2026MN HoldingsSubstationTwo consumer landing stations, southern region245.4m(The Star)
12 Mar 2026MN HoldingsSubstationConsumer substation for a data centre, southern region216m(The Star)
4 Feb 2026IOI PropertiesLand seller136.03 acres at Banting, to Bridge Data Centres740.68m(The Star)
4 Feb 2026BinastraDesign and buildCheras data centre503m(The Star)
16 Jan 2026MN HoldingsSubstationSubstation equipment for data-centre projects122.7m(The Star)

Values as reported from the companies’ Bursa filings by the outlets cited. Clients are mostly undisclosed.

  • Totals that check: Gamuda’s four 2026 data-centre contracts total RM7.00bn (1.72 + 1.71 + 1.79 + 1.78); SunCon’s Johor project totals RM2.51bn (570 + 1,020 + 920.8) (BusinessToday).
  • A headline that doesn’t: BusinessToday’s “RM8 billion” for SunCon on 5 Nov 2026 is all of SunCon’s 2026 new orders, not data-centre wins; the data-centre figure in the same article is RM6.75bn from six contracts (BusinessToday).
  • YTL Power: 150 MW delivered and 298 MW secured at Kulai in 3QFY26 (The Star).
  • Sime Darby Property: about RM7.6bn of lease value from two Elmina data centres on 20-year leases (The Edge), and a fund of up to RM1.25bn for data-centre and logistics assets (The Star).
  • Telekom Malaysia: about 70% of TM Nxera capacity pre-sold (NST).

What does it cost to build and run a data centre in Malaysia?

Build and rent benchmarks
BenchmarkMalaysiaSingaporeBasisSource
Construction costUS$10.06 per watt, KL and Johor BahruUS$15.39 per wattAbout 60 MW IT, air-cooled; excludes land and IT equipment(EdgeProp) (Turner & Townsend)
Construction costUS$9.6m/MW mid-range, US$12m/MW highUS$17.9m/MWIT or total MW not stated(The Edge)
Colocation rentNo public Johor or KL figureUS$330–475/kW/month, average US$403CBRE, Q1 2026(CBRE)
Rent ratioSingapore is about 2–3 times JohorNot givenCBRE(w.media)

Electricity per kW, which nobody publishes. From the all-in HV Ultra cost on our tariff page for a 100 MW site:

  1. At 80% load: 64.35 sen/kWh × 730 hours × 0.80 = RM375.8 per kW of maximum demand a month.
  2. At 100% load: 62.79 sen/kWh × 730 × 1.00 = RM458.4 per kW a month.
  3. Per kW of IT load at PUE 1.4 and 80% load: RM375.8 × 1.4 = RM526.1 a month.

Ringgit only; no exchange rate is applied. Tariff schedule valid to 31 Dec 2027; AFA and any change to the Connected Load Charge move it.

What are Malaysian data-centre platforms valued at?

No cap rates or yields for Malaysian data centres are public. The disclosed and reported deal points:

  • DayOne raised over US$2.0bn in a Series C priced at a 100% premium to its prior round; it did not disclose a valuation (DayOne, 5 Jan 2026).
  • Bain may sell about half of Bridge Data Centres at a reported value above US$4bn; this is a report, not a signed deal (w.media, 30 Jul 2026).
  • TIME dotCom sold 49% of AIMS to DigitalBridge at an enterprise value of RM3.2bn in 2022; no earnings multiple was given (NST).

What tax incentives can a data-centre investor get?

  • DESAC is the incentive built for data centres; see the DESAC page.
  • JS-SEZ: data centres are not listed among the eligible activities for the 5% rate in the official MIDA and IRDA text (MIDA and IRDA).
  • Malaysia Digital: lists cloud as an enabler, not data centres (MDEC).
  • Green allowance: the version for green data centres ended on 31 December 2023 (MIDA).
  • SST: 8% service tax on rental and leasing from 1 July 2025, above a RM1m threshold, with business-to-business exemptions (MOF); industrial machinery moved to 5% sales tax (MOF).
  • Carbon tax: announced for 2026 for iron, steel and energy, then delayed on 21 April 2026 with no new date (Reccessary).

Can Malaysian data centres import Nvidia GPUs?

Yes. Malaysia’s permit, in force since 14 July 2025, covers the export, transhipment and transit of high-performance AI chips, not their import (MITI). The details:

  • Chips are covered by technical thresholds (category 3U090 and related server categories), not by brand (MITI).
  • Exporters file an AI Chip Assessment form at least 30 days ahead; penalties reach RM20m for a company (MITI).
  • Customs seized 30 servers with advanced AI chips, about RM49.5m, at KLIA on 15 October 2026, the fifth case linked to one syndicate this year (Malay Mail); 72 servers worth RM52.92m were seized in June (The Star).
  • The US announced extra licence requirements for AI chip exports to Malaysia and Thailand on 13 May 2025 (BIS); we found no implementing rule. The 15 January 2026 US rule covers China and Macau, not Malaysia (Federal Register).

How can a data centre buy renewable power in Malaysia?

Renewable supply routes
RoutePriceTermsSource
CRESS (corporate renewable supply)20 sen/kWh access charge firm, 40 non-firmRP4(Energy Commission)
CRESS acceleration package14 sen/kWh fixed for 10 yearsProjects in operation by 31 Dec 2028(Bernama, 19 Oct 2026)
Green Electricity Tariff5, 4 or 3 sen/kWh premium1, 2 or 3-year commitment, from 1 Jul 2025(FMT)

The 30% renewable requirement is decided but its guidelines are not issued (see the rules tracker). New gas generation of up to 7,848 MW is being tendered for 2029–2031 (The Edge).

What are the risks, from the public record?

  • Reserved, not used: 58.6% of contracted power was used in August 2026 (Malay Mail), and unused allocations are to be charged (The Star).
  • Approvals: new non-AI data centres are frozen since 24 February 2026 (Malay Mail).
  • Water: Johor granted 21% of the data-centre water requested in 2024 (EdgeProp) and has approved only Tier 3–4 air-cooled designs since 10 March 2026 (Malay Mail); see water.
  • Chips: export-control enforcement at KLIA, and US rules still in flux (above).
  • Counts that disagree: Johor’s pipeline is 2.5 GW planned (Cushman & Wakefield), 2.7 GW (JLL) or 8.5 GW (Knight Frank), depending on what each counts (above).

What is not public

We could not confirm these from a published source as of 10 November 2026. Do not assume them:

  • Colocation rent per kW in Johor or Greater KL
  • Cap rates or yields for Malaysian data centres
  • Data-centre revenue for most Bursa companies
  • Megawatts for Google’s new campuses
  • The clients behind most hyperscale contracts
  • The text of the Data Centre Bill

Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.

Sources

Last checked 10 November 2026

Questions

How much data-centre capacity does Johor have?

1,110 MW of operating IT capacity and 602 MW under construction in H1 2026, per Cushman & Wakefield, with colocation vacancy of 0.7%.

How much has Google invested in Malaysia?

Google committed US$2bn in May 2024 (Elmina, operating) and US$15bn for 2027–2028 on 4 November 2026, for new campuses in Selangor and Negeri Sembilan.

Which Bursa companies have data-centre contracts?

In 2026: Gamuda (RM7.00bn across four contracts), Sunway Construction, IJM, Kerjaya Prospek, MN Holdings, Binastra and Mitrajaya, plus land sellers such as IOI Properties, Mah Sing, Crescendo and Paragon Globe.

What does electricity cost a data centre per kW in Malaysia?

About RM375.8 per kW of maximum demand a month at 80% load on the HV Ultra tariff, for a 100 MW site.