Johor had 1,110 MW of operating data-centre IT capacity in H1 2026, 602 MW under construction and colocation vacancy of 0.7% (Cushman & Wakefield via EdgeProp, 27 Aug 2026). Nationally, data centres drew 1,374 MW against 2,346 MW contracted in August 2026 (The Star), and TNB has signed supply for 61 projects with 8.35 GW of maximum demand (MBSB via TNB).
Google committed US$15bn for 2027–2028 on 4 November 2026 (Google), on top of AWS’s US$6.2bn (MIDA), Oracle’s US$6.5bn (MIDA) and Microsoft’s US$2.2bn (Microsoft). MIDA approved RM385.7bn of data-centre-related investment from 2021 to H1 2026; these are approvals, not money spent (MIDA).
- 1,110 MW
- Johor operating IT capacity, H1 2026 (C&W)
- 0.7%
- Johor colocation vacancy (C&W)
- 58.6%
- Contracted power actually used, Aug 2026 (Malay Mail)
- US$15bn
- Google’s 4 Nov 2026 commitment (Google)
- RM375.8 /kW/month
- Electricity per kW of maximum demand, HV Ultra, 80% load (calculated below)
How much data-centre capacity does Malaysia have?
Depends on who counts and what. The consultancies measure IT load; the government measures grid demand. They should not be added together.
| Source | Operating | Under construction | Pipeline | Scope and date |
|---|---|---|---|---|
| Cushman & Wakefield (EdgeProp) | 1,110 MW | 602 MW | 2,486 MW planned | Johor, IT load, H1 2026 |
| Knight Frank (EdgeProp) | 1,110 MW | Not given | 8,542 MW | Johor, IT load; pipeline scope not defined; Atlas 2026 |
| JLL (The Edge) | 850 MW completed | 1,800 MW | 2,700 MW | Johor Bahru, 2Q 2026, basis not stated |
| Knight Frank (Malay Mail) | 504.8 MW | 1,313 MW upcoming | Not given | Malaysia, IT load, Dec 2024 |
| As of | Actual draw | Compared with | Share | Source |
|---|---|---|---|---|
| Jun 2025 | 603 MW | 1,276 MW declared maximum demand | About 47% | (w.media) |
| Apr 2026 | 1,102 MW | 2,050 MW maximum approved demand | About 54% | (EdgeProp) |
| Aug 2026 | 1,374 MW | 2,346 MW contracted | 58.5–58.6% | (The Star) (Malay Mail) |
The comparison base changes each time (declared, approved, contracted), so the three shares are not a like-for-like trend.
TNB’s pipeline is larger again: 61 projects with 8.35 GW of maximum demand under supply agreements, 42 of them (5.65 GW) connected, with actual data-centre load of 1.26 GW in June 2026 (MBSB via TNB). Data centres were about 6% of TNB’s electricity sales (MBSB via TNB); 68% of secured capacity is in Johor (The Star).
Which campuses are being built, and how big?
Thirty campuses with the operator’s announced megawatts, whether that figure is IT load or total power, status and source. Where the source does not say, we say “not stated”.
| Operator | Campus | State | Announced MW | MW basis | Status | Source |
|---|---|---|---|---|---|---|
| YTL Power | YTL Green Data Center Park, Kulai | Johor | 1,200 planned (raised from 600); 298 contracted | Not stated | Operating; 200 MW more under construction (Jun 2026) | 25 Jun 2026 |
| AirTrunk | JHB1 and JHB2, Johor Bahru and Iskandar Puteri | Johor | Over 420 combined | IT load | JHB1 operating since Jul 2024; JHB1 and JHB2 almost fully contracted (Apr 2026) | 30 Apr 2026 |
| AirTrunk | JHB3 and JHB4, Iskandar Puteri | Johor | 280 combined | IT load | Planned (Apr 2026) | 30 Apr 2026 |
| DayOne | Nusajaya and Kempas Tech Parks | Johor | 390 in service, or over 478 operational (same company page) | Not stated | Operating | Read 10 Nov 2026 |
| Princeton Digital Group | JH1, Sedenak Tech Park | Johor | 200 (raised from 150) | Not stated | Phase 1 (52 MW) delivered Jul 2024; buildings 3 and 4 under construction (Dec 2025) | 17 Dec 2025 |
| STT GDC | STT Johor, Nusa Cemerlang | Johor | Up to 166 (raised from 120) | IT load | Under construction; Johor 1 (16 MW) due end-2026 | 24 Feb 2025 |
| Vantage Data Centers | JHB1, Sedenak Tech Park | Johor | Over 300 across 3 buildings at full build | IT load | Acquired from Yondr (Nov 2025) | 24 Nov 2025 |
| Bridge Data Centres | MY06, Sedenak Tech Park (ByteDance) | Johor | 110 across 3 buildings | Not stated | Phase 1 opened Oct 2022 | 20 Oct 2022 |
| K2 Strategic | JHR1, Sedenak Tech Park | Johor | 300 | Gross power | TNB supply agreement signed (Sep 2023); later status not published | 15 Sep 2023 |
| Racks Central | AIDC campus, Pasir Gudang | Johor | 510 campus; phase 1 70 | Not stated | Under construction; phase 1 due 1Q 2027 | 30 Jun 2026 |
| TM Nxera | Iskandar Puteri campus | Johor | Over 200; 280 supply secured | 280 = grid supply | Under construction; phase 1 (64 MW) from Sep 2026 | 12 Jan 2026 |
| NTT DATA | JHB10, Gelang Patah | Johor | About 290; first building 48 | IT load | Planned; first building Apr 2027 | 6 Dec 2024 |
| Bitdeer AI | A201 and A202, Johor Bahru | Johor | 86.8 | Not stated | Energisation 1Q and 3Q 2027 | 14 Oct 2026 |
| EdgeConneX | Johor | Johor | 36, up to 160 | Not stated | Not stated | Read 10 Nov 2026 |
| Open DC | JB1, Johor Bahru | Johor | 20 | Not stated | Operating since 2015 | 23 Sep 2026 |
| Elmina Business Park | Selangor | Not disclosed | n/a | Operating (Nov 2026) | 4 Nov 2026 | |
| New campuses, Selangor and Negeri Sembilan | Selangor; Negeri Sembilan | Not disclosed | n/a | Planned, 2027–2028 | 4 Nov 2026 | |
| AIMS (TIME dotCom joint venture) | New AI data centre, Cyberjaya | Selangor | Up to 200, subject to engineering | Not stated | Land acquired; completion targeted 2027 | 6 Feb 2026 |
| Digital Realty | KUL10, KUL11 and a future site, Cyberjaya | Selangor | About 32 | IT load | KUL10 and KUL11 operating; future site mid-2028 | 8 Jun 2026 |
| NTT DATA | Cyberjaya campus (CBJ1–CBJ6) | Selangor | CBJ5 and CBJ6: 22 | Facility load | Operating | 10 Oct 2023 |
| Bitdeer AI | A101–A103, Cyberjaya | Selangor | About 71.5 | Not stated | A103 energisation 1Q 2028 | 14 Oct 2026 |
| Microsoft | Malaysia West region (3 availability zones) | Greater Kuala Lumpur | Not disclosed | n/a | Operating since 28 May 2025 | 28 May 2025 |
| AWS | Asia Pacific (Malaysia) region (3 availability zones) | Not disclosed | Not disclosed | n/a | Operating since Aug 2024 | 21 Aug 2024 |
| Google affiliate (Pearl Computing); Gamuda builds | Port Dickson campus, 389 acres | Negeri Sembilan | 500–1,000 planned at land sale | Not stated | Under construction; Gamuda contracts to 2028 | 1 Sep 2026 |
| Vena Nexus | Nexus Yang, Senawang | Negeri Sembilan | About 350 initial | IT load | Ground broken (Mar 2026) | 3 Mar 2026 |
| Open DC | PE2, Bayan Lepas | Penang | 30, target 100 | Not stated | About 15 MW energised (Sep 2026) | 23 Sep 2026 |
| Privasia (Silverstreams) | Bagan Datuk | Perak | Phase 1 10.06 | Not stated | Under construction; go-live end-2027 or early 2028 | 10 Apr 2026 |
| Victoria Data Centre | Jasin | Melaka | About 100 (also given as up to 96) | Not stated | Intention announced (Feb 2026) | 5 Feb 2026 |
| FutureData | FutureData Park, Kota Samarahan | Sarawak | 200 (2023), later 500 (2024) | Not stated | Planned; no 2026 update published | 9 Oct 2024 |
| Firmus | Two AI Factory sites (OpenAI anchor) | Not disclosed | Not disclosed | n/a | Status not stated (Sep 2026) | 8 Sep 2026 |
Download the ledger as CSV, free to reuse with credit (CC BY 4.0). Announced MW is the operator’s figure, often full build-out, and is not additive across rows.
How much have the big technology companies committed?
| Company | Amount | Period | Where | Type | Source |
|---|---|---|---|---|---|
| US$15bn | 2027–2028 | New campuses in Selangor and Negeri Sembilan | Commitment (4 Nov 2026) | (Google) | |
| US$2bn | Not stated | Elmina, Selangor; cloud region | Commitment (30 May 2024); operating | (Google) | |
| Oracle | More than US$6.5bn | Not stated | Malaysia, site not named | Commitment (2 Oct 2024) | (MIDA) |
| AWS | About US$6.2bn | Through 2038 | Malaysia region, 3 zones | Commitment; region open since Aug 2024 | (MIDA) |
| Microsoft | US$2.2bn | 4 years from May 2024 | Malaysia West (Greater KL); Johor Bahru region planned | Commitment; region live 28 May 2025 | (Microsoft) (Microsoft) |
| ByteDance | About RM10bn | Not stated | Malaysia; RM1.5bn more at Sedenak | Proposal cited by a minister (Jun 2024) | (MIDA) |
| YTL Power with Nvidia | Not stated by YTL | From 2024 | Kulai, Johor; 500 MW | Commitment (8 Dec 2023) | (YTL Power) |
| Alibaba Cloud | No Malaysia amount | Not given | Second region, Johor | Opened 9 Jun 2026 | (Bernama) |
| Tencent Cloud | No amount | No date | Johor | Planned (18 Aug 2026) | (Tencent) |
| OpenAI via Firmus | Not disclosed | Multi-year | Two Malaysian sites | Compute contract (8 Sep 2026) | (Firmus) |
The US$15bn, US$6.5bn, US$6.2bn and US$2.2bn commitments total US$29.9bn, or US$31.9bn with Google’s 2024 US$2bn. They cover cloud regions, skills and energy as well as buildings, and are pledges, not spending to date. Google’s “more than 1 GW” in the 2026 announcement is new clean-energy generation for the grid, not data-centre capacity (Google).
How much data-centre investment has Malaysia approved?
| Figure | What it counts | Source |
|---|---|---|
| RM385.7bn | Data-centre-related investment approved, 2021 to H1 2026 | (MIDA, 14 Sep 2026) |
| RM95.8bn | Data-centre and cloud projects approved in H1 2026, close to 44% of all approvals | (MIDA, 28 Aug 2026) |
| RM34.6bn, 33 projects | Data centres and cloud computing, Q1 2026 | (MIDA) |
| 143 projects, RM144.4bn | Data-centre projects approved, 2021 to Jun 2025 | (The Star (Dewan Rakyat)) |
| 27 projects, RM225.97bn | Approved by the Data Centre Task Force to Jul 2026: Johor 16, Selangor 10, Negeri Sembilan 1 | (The Star (written reply)) |
The series use different definitions; do not subtract one from another to get annual figures. MIDA gives 2025’s total approvals for all sectors as RM426.7bn in one release and RM431.1bn in a later one (MIDA).
Which Bursa-listed companies earn from data centres?
Contractors, landowners, power-equipment firms and a few owners. Most do not report data-centre revenue separately, so contract awards are the visible exposure, and an award is not revenue already earned.
| Date | Company | Role | Contract or deal | RM | Source |
|---|---|---|---|---|---|
| 5 Nov 2026 | Sunway Construction | Main contractor | Hyperscale data centre, Bandar Serendah, Selangor (client not disclosed) | 1.74bn | (The Edge) |
| 4 Nov 2026 | Sunway Construction | MEP contractor | Additional MEP fit-out, Johor data centre; lifts that project to RM2.51bn | 920.8m | (The Star) |
| 13 Oct 2026 | MN Holdings | Substation | Two 275kV consumer landing stations for a data centre, central region | 293.88m | (The Star) |
| 3 Sep 2026 | Kerjaya Prospek | MEP contractor | MEP fit-out, data centre at Iskandar Puteri | 858m | (The Star) |
| 28 Aug 2026 | Gamuda | Main contractor | Two hyperscale data centres, Port Dickson (US technology client, not named) | 3.57bn | (EdgeProp) |
| 20 Aug 2026 | Mah Sing | Land seller | 78.8 acres at Southville City, Sepang, at RM180 psf | 617.9m | (The Star) |
| 5 Aug 2026 | Gamuda | Main contractor | Hyperscale data centre, Port Dickson | 1.71bn | (The Star) |
| 3 Aug 2026 | Sunway Construction | MEP contractor | MEP fit-out, Johor data centre (US technology client) | 1.02bn | (BusinessToday) |
| 27 Jul 2026 | SNS Network Technology | Server supplier | AI servers for a data centre in Malaysia (US$298.66m) | About 1.22bn | (The Star) |
| 1 Jul 2026 | Binastra | Design and build | Phase 2, Cheras data centre | 491.2m | (The Star) |
| 23 Jun 2026 | Paragon Globe | Land seller | About 65 acres, Tanjung Kupang, to a DayOne unit | 398.1m | (The Star) |
| 17 Jun 2026 | Sunway Construction | Substation | Change orders for substations at two Johor data centres; total RM865.6m | 664.4m | (The Star) |
| 17 Apr 2026 | Sunway Construction | Main contractor | Hyperscale data centre, Bandar Serendah, Selangor | 1.75bn | (EdgeProp) |
| 17 Apr 2026 | Gamuda | Main contractor | Hyperscale data centre, Port Dickson | 1.72bn | (Malay Mail) |
| 13 Apr 2026 | Mitrajaya | Main contractor | Early works, NEXTDC KL1 stage 4 (main works now RM844.66m) | 54m | (The Star) |
| 9 Apr 2026 | Crescendo | Land seller | 49.72 acres, Kota Tinggi, to Digital Edge | 346.53m | (The Star) |
| 1 Apr 2026 | IJM | Main contractor | Package 2 core and shell, Elmina Business Park (for Sime Darby Property) | 658.01m | (The Star) |
| 25 Mar 2026 | MN Holdings | Substation | Two consumer landing stations, southern region | 245.4m | (The Star) |
| 12 Mar 2026 | MN Holdings | Substation | Consumer substation for a data centre, southern region | 216m | (The Star) |
| 4 Feb 2026 | IOI Properties | Land seller | 136.03 acres at Banting, to Bridge Data Centres | 740.68m | (The Star) |
| 4 Feb 2026 | Binastra | Design and build | Cheras data centre | 503m | (The Star) |
| 16 Jan 2026 | MN Holdings | Substation | Substation equipment for data-centre projects | 122.7m | (The Star) |
Values as reported from the companies’ Bursa filings by the outlets cited. Clients are mostly undisclosed.
- Totals that check: Gamuda’s four 2026 data-centre contracts total RM7.00bn (1.72 + 1.71 + 1.79 + 1.78); SunCon’s Johor project totals RM2.51bn (570 + 1,020 + 920.8) (BusinessToday).
- A headline that doesn’t: BusinessToday’s “RM8 billion” for SunCon on 5 Nov 2026 is all of SunCon’s 2026 new orders, not data-centre wins; the data-centre figure in the same article is RM6.75bn from six contracts (BusinessToday).
- YTL Power: 150 MW delivered and 298 MW secured at Kulai in 3QFY26 (The Star).
- Sime Darby Property: about RM7.6bn of lease value from two Elmina data centres on 20-year leases (The Edge), and a fund of up to RM1.25bn for data-centre and logistics assets (The Star).
- Telekom Malaysia: about 70% of TM Nxera capacity pre-sold (NST).
What does it cost to build and run a data centre in Malaysia?
| Benchmark | Malaysia | Singapore | Basis | Source |
|---|---|---|---|---|
| Construction cost | US$10.06 per watt, KL and Johor Bahru | US$15.39 per watt | About 60 MW IT, air-cooled; excludes land and IT equipment | (EdgeProp) (Turner & Townsend) |
| Construction cost | US$9.6m/MW mid-range, US$12m/MW high | US$17.9m/MW | IT or total MW not stated | (The Edge) |
| Colocation rent | No public Johor or KL figure | US$330–475/kW/month, average US$403 | CBRE, Q1 2026 | (CBRE) |
| Rent ratio | Singapore is about 2–3 times Johor | Not given | CBRE | (w.media) |
Electricity per kW, which nobody publishes. From the all-in HV Ultra cost on our tariff page for a 100 MW site:
- At 80% load: 64.35 sen/kWh × 730 hours × 0.80 = RM375.8 per kW of maximum demand a month.
- At 100% load: 62.79 sen/kWh × 730 × 1.00 = RM458.4 per kW a month.
- Per kW of IT load at PUE 1.4 and 80% load: RM375.8 × 1.4 = RM526.1 a month.
Ringgit only; no exchange rate is applied. Tariff schedule valid to 31 Dec 2027; AFA and any change to the Connected Load Charge move it.
What are Malaysian data-centre platforms valued at?
No cap rates or yields for Malaysian data centres are public. The disclosed and reported deal points:
- DayOne raised over US$2.0bn in a Series C priced at a 100% premium to its prior round; it did not disclose a valuation (DayOne, 5 Jan 2026).
- Bain may sell about half of Bridge Data Centres at a reported value above US$4bn; this is a report, not a signed deal (w.media, 30 Jul 2026).
- TIME dotCom sold 49% of AIMS to DigitalBridge at an enterprise value of RM3.2bn in 2022; no earnings multiple was given (NST).
What tax incentives can a data-centre investor get?
- DESAC is the incentive built for data centres; see the DESAC page.
- JS-SEZ: data centres are not listed among the eligible activities for the 5% rate in the official MIDA and IRDA text (MIDA and IRDA).
- Malaysia Digital: lists cloud as an enabler, not data centres (MDEC).
- Green allowance: the version for green data centres ended on 31 December 2023 (MIDA).
- SST: 8% service tax on rental and leasing from 1 July 2025, above a RM1m threshold, with business-to-business exemptions (MOF); industrial machinery moved to 5% sales tax (MOF).
- Carbon tax: announced for 2026 for iron, steel and energy, then delayed on 21 April 2026 with no new date (Reccessary).
Can Malaysian data centres import Nvidia GPUs?
Yes. Malaysia’s permit, in force since 14 July 2025, covers the export, transhipment and transit of high-performance AI chips, not their import (MITI). The details:
- Chips are covered by technical thresholds (category 3U090 and related server categories), not by brand (MITI).
- Exporters file an AI Chip Assessment form at least 30 days ahead; penalties reach RM20m for a company (MITI).
- Customs seized 30 servers with advanced AI chips, about RM49.5m, at KLIA on 15 October 2026, the fifth case linked to one syndicate this year (Malay Mail); 72 servers worth RM52.92m were seized in June (The Star).
- The US announced extra licence requirements for AI chip exports to Malaysia and Thailand on 13 May 2025 (BIS); we found no implementing rule. The 15 January 2026 US rule covers China and Macau, not Malaysia (Federal Register).
How can a data centre buy renewable power in Malaysia?
| Route | Price | Terms | Source |
|---|---|---|---|
| CRESS (corporate renewable supply) | 20 sen/kWh access charge firm, 40 non-firm | RP4 | (Energy Commission) |
| CRESS acceleration package | 14 sen/kWh fixed for 10 years | Projects in operation by 31 Dec 2028 | (Bernama, 19 Oct 2026) |
| Green Electricity Tariff | 5, 4 or 3 sen/kWh premium | 1, 2 or 3-year commitment, from 1 Jul 2025 | (FMT) |
The 30% renewable requirement is decided but its guidelines are not issued (see the rules tracker). New gas generation of up to 7,848 MW is being tendered for 2029–2031 (The Edge).
What are the risks, from the public record?
- Reserved, not used: 58.6% of contracted power was used in August 2026 (Malay Mail), and unused allocations are to be charged (The Star).
- Approvals: new non-AI data centres are frozen since 24 February 2026 (Malay Mail).
- Water: Johor granted 21% of the data-centre water requested in 2024 (EdgeProp) and has approved only Tier 3–4 air-cooled designs since 10 March 2026 (Malay Mail); see water.
- Chips: export-control enforcement at KLIA, and US rules still in flux (above).
- Counts that disagree: Johor’s pipeline is 2.5 GW planned (Cushman & Wakefield), 2.7 GW (JLL) or 8.5 GW (Knight Frank), depending on what each counts (above).
What is not public
We could not confirm these from a published source as of 10 November 2026. Do not assume them:
- Colocation rent per kW in Johor or Greater KL
- Cap rates or yields for Malaysian data centres
- Data-centre revenue for most Bursa companies
- Megawatts for Google’s new campuses
- The clients behind most hyperscale contracts
- The text of the Data Centre Bill
Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.
Sources
- The Star, unused power allocations (15 Oct 2026)
- Malay Mail, data-centre power share heading for 21% (4 Nov 2026)
- Malay Mail, new non-AI data centres frozen (24 Feb 2026)
- Malay Mail, Johor refuses high-water designs (10 Mar 2026)
- EdgeProp, water granted at 21–28% of requests
- Malay Mail, Gamuda RM1.72bn Port Dickson contract (17 Apr 2026)
- The Star, Gamuda RM1.71bn Port Dickson job (5 Aug 2026)
- TechWire Asia, Open DC Penang to 100 MW (Sep 2026)
- EdgeProp, data centres using about half of approved power and water capacity
- The Star, SNS Network RM1.22bn server contract (27 Jul 2026)
- EdgeProp, Cushman & Wakefield H1 2026 Johor figures (27 Aug 2026)
- The Edge via TNB newsclip, JLL Malaysia 2Q 2026 (28 Apr 2026)
- EdgeProp, Knight Frank Data Centre Atlas 2026 (31 Jul 2026)
- Malay Mail, Knight Frank Malaysia data centre report (23 Dec 2024)
- w.media, Dewan Rakyat answer on declared demand (6 Nov 2025)
- The Star, data centres using 58.5% of contracted power (28 Oct 2026)
- Borneo Post via TNB newsclip, TNB data-centre pipeline after 2Q26 results (2 Sep 2026)
- The Star, data-centre demand to energise TNB growth (13 Jul 2026)
- Google, US$15 billion Malaysia investment (4 Nov 2026)
- Google, advancing Malaysia together (30 May 2024)
- Microsoft, US$2.2 billion Malaysia investment (2 May 2024)
- Microsoft, Malaysia West cloud region (28 May 2025)
- Microsoft Azure blog, cloud infrastructure in Asia (9 Oct 2025)
- MIDA, AWS Asia Pacific (Malaysia) region (22 Aug 2024)
- MIDA, Oracle to invest US$6.5 billion (2 Oct 2024)
- MIDA, ByteDance plans RM10 billion AI investment (7 Jun 2024)
- YTL Power, AI development with Nvidia (8 Dec 2023)
- Bernama, Alibaba Cloud second Malaysian region in Johor (9 Jun 2026)
- Tencent Cloud, first Malaysian region (18 Aug 2026)
- Firmus, OpenAI anchor customer and Malaysia expansion (8 Sep 2026)
- MIDA, next phase for the data-centre sector (14 Sep 2026)
- MIDA, H1 2026 investment performance (28 Aug 2026)
- MIDA, Q1 2026 approved investments (8 Jun 2026)
- The Star, RM144.4bn from data centres approved since 2021 (5 Nov 2025)
- The Star, task force approved 27 data-centre projects (14 Oct 2026)
- MIDA and IRDA, JS-SEZ incentive snapshot (Feb 2025)
- Ministry of Finance, revision to the expanded SST (28 Jun 2025)
- Ministry of Finance, expansion of SST scope (Jun 2025)
- MIDA, green incentives under Budget 2024 (27 Dec 2023)
- MDEC, Malaysia Digital tax incentive
- Reccessary, Malaysia delays carbon tax (23 Apr 2026)
- EdgeProp, KL and JB among lower-cost construction markets, Turner & Townsend (2 Nov 2026)
- Turner & Townsend, data centre cost index 2026–27 (29 Oct 2026)
- The Edge, Cushman & Wakefield construction cost guide 2026 (1 Apr 2026)
- CBRE, global data center trends 2026 (17 Jun 2026)
- w.media, CBRE on Southeast Asia supply (12 Jun 2025)
- DayOne, Series C financing (5 Jan 2026)
- w.media, bidders for a Bridge Data Centres stake (30 Jul 2026)
- NST, TIME sells AIMS stake to DigitalBridge (22 Nov 2022)
- MITI, Malaysia regulates trade of US AI chips (14 Jul 2025)
- MITI, Directive No.1/2025 on advanced AI chips (updated 8 Dec 2025)
- MITI, industry guideline on advanced AI chips (Jul 2025)
- US BIS, rescission of the AI diffusion rule (13 May 2025)
- Federal Register, revision to licence review policy for advanced computing (15 Jan 2026)
- Malay Mail, KLIA customs seizes RM49.5m in AI chips (28 Oct 2026)
- The Star, customs seizes 72 servers with AI chips (26 Jun 2026)
- Energy Commission, CRESS system access charges (RP4)
- Bernama, CRESS acceleration package (19 Oct 2026)
- Free Malaysia Today, Green Electricity Tariff premiums cut (2 Jul 2025)
- The Edge, new gas generation round (Jul 2026)
- The Edge, SunCon Bandar Serendah award (5 Nov 2026)
- The Star, SunCon RM920.8m additional Johor contract (4 Nov 2026)
- BusinessToday, SunCon and Gamuda data-centre wins (5 Nov 2026)
- The Star, MN Holdings data-centre infrastructure contracts (13 Oct 2026)
- The Star, Kerjaya Prospek RM858m Johor contract (3 Sep 2026)
- EdgeProp, Gamuda RM3.57bn Port Dickson contracts (1 Sep 2026)
- The Star, Mah Sing land sale (20 Aug 2026)
- BusinessToday, SunCon RM1.02bn Johor fit-out (3 Aug 2026)
- The Star, Binastra RM491.2m data-centre project (1 Jul 2026)
- The Star, Paragon Globe land disposal (23 Jun 2026)
- The Star, SunCon Johor substation contracts rise to RM865.6m (18 Jun 2026)
- The Star, Sime Darby Property New Economy Venture fund (9 Jun 2026)
- EdgeProp, SunCon RM1.75bn Bandar Serendah contract (17 Apr 2026)
- The Star, Mitrajaya RM54m early works (13 Apr 2026)
- The Star, Crescendo disposes of Johor land (9 Apr 2026)
- The Star, Sime Darby Property awards IJM RM658.01m (1 Apr 2026)
- The Star, MN Holdings RM245m CLS contracts (25 Mar 2026)
- The Star, MN Holdings RM216m substation contract (12 Mar 2026)
- The Star, IOI Properties sells industrial land (4 Feb 2026)
- The Star, Binastra RM503m data-centre project (4 Feb 2026)
- The Star, MN Holdings RM122.7m data-centre power works (16 Jan 2026)
- The Edge, Sime Darby Property data-centre leases (3 Oct 2026)
- The Star, YTL Power stamping its mark on the data-centre sector (29 Jun 2026)
- NST, TM Nxera 70% take-up (21 Aug 2026)
Last checked 10 November 2026