The AWS Asia Pacific (Malaysia) region, ap-southeast-5, has been open since 21 August 2024 with three availability zones (AWS, 21 Aug 2024). AWS said it plans to invest about US$6.2 billion (RM29.2 billion) in Malaysia through 2038 (MIDA, 22 Aug 2024).
AWS does not publish where the zones are or how many megawatts they draw. An Amazon unit agreed in September 2026 to buy about 45 acres in Sepang, Selangor, for RM316.84 million, a deal not yet completed (w.media, 29 Sep 2026).
- US$6.2bn
- Planned investment through 2038 (MIDA, 22 Aug 2024)
- 3 zones
- Availability zones at launch (AWS, 21 Aug 2024)
- RM316.84m
- Conditional Sepang land purchase (w.media, 29 Sep 2026)
- 3,500 jobs a year
- Company estimate, at suppliers and contractors, through 2038 (AWS, 21 Aug 2024)
What is the AWS Malaysia region?
- Name: Asia Pacific (Malaysia), API name ap-southeast-5, the first AWS infrastructure region in the country (AWS, 21 Aug 2024).
- Zones: three, each with independent power, cooling and physical security. Locations are not given (MIDA, 22 Aug 2024).
- Other infrastructure: four CloudFront locations and two Direct Connect locations in Malaysia at launch (AWS, 21 Aug 2024).
How much is AWS investing in Malaysia?
Two figures have been published. In March 2023 the plan was at least US$6 billion (RM25.5 billion) by 2037 (Digital News Asia, 2 Mar 2023). At launch it was about US$6.2 billion (RM29.2 billion) through 2038 (MIDA, 22 Aug 2024). Both are plans, not spending to date.
The company estimates the region will add about US$12.1 billion to GDP and support more than 3,500 full-time-equivalent jobs a year at external businesses through 2038 (AWS, 21 Aug 2024). These are company estimates.
What land and water deals are public?
- Sepang land: Amazon Data Services Malaysia agreed to buy 183,973 sq m (about 45.46 acres by our conversion) of freehold commercial land from Sunsuria City for RM316.84m, “to host data processing services and infrastructure”. Completion is expected in the second quarter of 2027 and needs state consent (w.media, 29 Sep 2026) (The Star, 28 Sep 2026).
- Reclaimed water: three agreements signed on 13 November 2025 for the Selangor water operator to supply industrial reclaimed water to AWS, described as the first such use by a data-centre operator in the Klang Valley. No volume, site or start date was given (EdgeProp, 14 Nov 2025).
What is not public
We could not confirm these from a published source as of 11 November 2026. Do not assume them:
- The sites of the three availability zones
- Megawatts for the region or any site
- Spending to date against the US$6.2bn plan
- Reclaimed-water volumes and which sites they serve
- Builders of any AWS data centre in Malaysia
- A Malaysia-specific renewable energy purchase
Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.
Sources
- MIDA, AWS Asia Pacific (Malaysia) region (22 Aug 2024)
- AWS, Asia Pacific (Malaysia) region now open (21 Aug 2024)
- w.media, Amazon unit to buy Sepang land (29 Sep 2026)
- Digital News Asia, AWS to invest US$6bn by 2037 (2 Mar 2023)
- The Star, Sunsuria to dispose of Selangor land (28 Sep 2026)
- EdgeProp, Air Selangor and AWS reclaimed water agreements (14 Nov 2025)
Last checked 11 November 2026