Equinix in Malaysia: JH1, KL1 and the two sites being built

Equinix publishes cabinets and floor space for its Malaysian sites, not megawatts.

Contents

Equinix operates two data centres in Malaysia, JH1 at Nusajaya Tech Park in Johor and KL1 in Cyberjaya, both opened on 27 May 2024 (Equinix, 27 May 2024). It is building JH2 in Johor, an initial US$201 million investment due to launch in the third quarter of 2027 (Equinix, 10 Nov 2025), and has announced KL2 in Cyberjaya at over US$190 million (Equinix, 11 May 2026).

The company publishes cabinet counts and floor space, not megawatts. The four announced investment figures add up to at least US$531 million, by our addition.

4 sites
Two operating, two planned or under construction (Equinix, 11 May 2026)
US$201m
Initial investment in JH2, Johor (Equinix, 10 Nov 2025)
2,225 cabinets
JH2 at launch, expected Q3 2027 (Equinix, 10 Nov 2025)
US$531m
Sum of the four announced investments, at least (our addition from the table below)

Where are Equinix’s data centres in Malaysia?

Equinix sites in Malaysia
SiteLocationSize as publishedInvestment as announcedStatusSource
JH1Nusajaya Tech Park, Iskandar Puteri, JohorUp to 500 cabinets; 1,800 sq m of colocation spaceUS$40m initialOperating since 27 May 2024(Equinix, 30 Nov 2022) (Equinix, 27 May 2024)
KL1Cyberjaya900 cabinets and 2,630 sq m at full build; Phase 2 completeMore than US$100m additionalOperating since 27 May 2024; Phase 2 from May 2025(Equinix, 11 Jun 2023) (w.media, 7 May 2025)
JH2Johor, within the Johor–Singapore Special Economic Zone2,225 cabinetsUS$201m initialTopped out; launch expected Q3 2027(Equinix, 10 Nov 2025)
KL2Cyberjaya, less than 1 km from KL1More than 2,200 cabinets at full buildOver US$190m totalAnnounced 11 May 2026; no opening date(Equinix, 11 May 2026)

Total: 40 + 100 + 201 + 190 = US$531m, at least. The figures mix “initial”, “additional” and “total” investment, and Equinix publishes no such total.

What does Equinix say about power?

  • Its Malaysian data centres are “100% covered by renewables”, and KL2 targets full renewable coverage from its first day. The instruments used are not specified (Equinix, 27 May 2024) (Equinix, 11 May 2026).
  • KL2 and JH2 are designed with liquid cooling for AI workloads (Equinix, 11 May 2026) (w.media, 30 Oct 2025).
  • More than two-thirds of KL1 customers operate across several metros (Equinix, 11 May 2026).

Conflicting figures

Megawatts appear only in trade press, and some published sizes changed.

Conflicting figures and what each one is
PointCompanyTrade press
JH1 capacityNot published; 500 cabinets (Equinix, 27 May 2024)6 MW, basis not stated (w.media, 30 Oct 2025)
JH2 size2,225 cabinets, launch Q3 2027 (Equinix, 10 Nov 2025)Phase 1 of 7.2 MW, and a possible 77 MW campus from an unnamed source (w.media, 30 Oct 2025)
JH1 colocation space1,960 sq m at announcement (Equinix, 30 Nov 2022)1,800 sq m at opening (Equinix, 27 May 2024)

What is not public

We could not confirm these from a published source as of 11 November 2026. Do not assume them:

  • Megawatts, IT or total, for JH1, KL1, JH2 or KL2
  • Land area and ownership for JH1 and KL1
  • An opening date for KL2
  • Builders of any site
  • How the 100% renewable coverage is achieved in Malaysia
  • Any jobs or GDP estimate

Croutons Research publishes open data and methods on AI data centres in Malaysia. See the open method for measuring AI work per megawatt.

Sources

Last checked 11 November 2026

Questions

Does Equinix have a data centre in Malaysia?

Yes, two: JH1 in Iskandar Puteri, Johor, and KL1 in Cyberjaya. Both opened on 27 May 2024.

What is Equinix building in Johor?

JH2, a second Johor data centre with 2,225 cabinets and an initial investment of US$201 million, expected to launch in the third quarter of 2027.

How many megawatts are Equinix’s Malaysian data centres?

Equinix does not publish megawatts for them. Trade press gives 6 MW for JH1 and 7.2 MW for the first phase of JH2, without stating the basis.