Malaysian data centres were using 1,374 MW of the 2,346 MW they had contracted in August 2026, or 58.6% (w.media). The published charge for reserved but unused power is TNB’s Connected Load Charge: RM8.50 a month for each kW that recorded maximum demand falls short of 85% of declared demand in years 1 to 4, and of 75% in years 5 and 6 (TNB).
In October 2026 the MITI minister said operators are charged for allocated capacity whether they use it or not, and that those who do not pay will not be allowed to operate (The Star, 15 Oct 2026). The Deputy Prime Minister said the charge had been increased (The Star, 21 Oct 2026). No new rate or start date has been published. At the published rate, each megawatt below the line costs RM8,500 a month.
- 58.6%
- Share of contracted power data centres used, Aug 2026 (w.media)
- RM8.50 /kW/month
- Connected Load Charge on the shortfall (TNB)
- 85%
- Of declared demand: the line in years 1 to 4; 75% in years 5 and 6 (TNB)
- RM8,500 a month
- Per megawatt below the line, at the published rate (8.50 × 1,000 kW)
Which position are you in?
| Your position | What the public record says | What to do |
|---|---|---|
| Recorded maximum demand is at or above 85% of declared demand (75% in years 5 and 6) | No Connected Load Charge under the published rule (TNB) | Nothing to pay under the published rule. Watch for the new rate. |
| Recorded maximum demand is below the line | RM8.50 a month per kW of shortfall, for six years from connection; TNB notes the rate can change (TNB) | Work out the charge below, then choose: raise the load, ask TNB about the declared figure, or pay. |
| Capacity is allocated and the site is not yet drawing it | Charged for allocated capacity whether used or not; non-payers will not be allowed to operate (The Star, 15 Oct 2026) | Ask TNB in writing which charge applies to you and from when. The new rate is not published. |
The charge applies to new medium-voltage and high-voltage customers for six years (TNB). It is separate from the capacity and network charges, which are billed on recorded peak maximum demand (Energy Commission).
How much is the charge? A worked example
Take a campus with 100 MW declared that uses 58.6 MW, the national share in August 2026.
| Step | Calculation | Result |
|---|---|---|
| The line, years 1 to 4 | 85% × 100 MW | 85.0 MW |
| Shortfall | 85.0 − 58.6 MW | 26.4 MW |
| Connected Load Charge | 26,400 kW × RM8.50 | RM224,400 a month |
| Per year | × 12 | RM2.69m |
| In years 5 and 6 | 75% × 100 − 58.6 = 16.4 MW shortfall | RM139,400 a month |
For scale only: if the national figures were one customer, 85% of 2,346 MW is 1,994.1 MW, the shortfall against 1,374 MW is 620.1 MW, and the charge would be RM5.27m a month. Real bills are worked out customer by customer, and sites past their sixth year are outside the rule.
Calculate it for your site
- The line
- 85.0 MW
- Shortfall
- 26.4 MW
- Per month
- RM224,400
- Per year
- RM2.69m
RM8.50 is the published rate. Ministers say the charge has been raised but no new rate is published, so the rate is yours to change. An estimate, not a TNB bill.
What can an operator do about it?
There are three responses, and the public record supports each to a different degree.
| Option | What it changes | What is known |
|---|---|---|
| Raise the load to the line | Removes the shortfall, so the charge stops | The line is 85% of declared demand in years 1 to 4 and 75% in years 5 and 6 (TNB) |
| Ask TNB about the declared figure | A lower declared demand lowers the line | Whether declared demand can be revised downward, and on what terms, is not published. Ask TNB for the terms in writing. |
| Pay the charge | Keeps the allocation for later phases | RM8.50 per kW of shortfall a month at the published rate; the raised rate is not published (The Star, 21 Oct 2026) |
The policy reason is grid planning. Data centres are about 7% of Peninsular electricity demand in 2026 and are forecast to reach 21% by 2030 (Malay Mail, 4 Nov 2026), with 8.39 GW of peak demand projected for 2030 (Malay Mail, Oct 2026). Capacity that is booked and not drawn is held back from other applicants.
What does each megawatt in use have to earn?
A megawatt that is drawn carries the fixed charges on the bill: RM21.76 of capacity charge and RM23.06 of network charge per kW of peak maximum demand each month (Energy Commission). That is RM44.82 per kW, or RM44,820 per megawatt a month, before any energy is billed. The energy charge and the all-in cost per kWh are worked through on the electricity tariff page.
So two numbers decide what a contracted megawatt returns: how much of it is in use, and how much work each megawatt in use delivers. This page covers the first. For AI halls the second is answers served per megawatt, which the open method paper defines and the energy per query page works through.
What is not public
We could not confirm these from a published source as of 15 November 2026. Do not assume them:
- The raised Connected Load Charge rate and its start date
- Whether RM8.50 is the old rate or the raised one
- Whether declared demand can be revised downward, and on what terms
- How the charge treats a campus that is energised in phases
- Booked and used megawatts for any single operator
Sources
- Energy Commission, TNB tariff schedule RP4 (MyEnergyStats copy)
- The Star, data centres to bear costs (21 Oct 2026)
- TNB, charges and penalties (Connected Load Charge)
- The Star, unused power allocations (15 Oct 2026)
- w.media, contracted versus used capacity
- Malay Mail, data-centre power share heading for 21% (4 Nov 2026)
- Malay Mail, 8.39 GW by 2030 (Oct 2026)