No state wins on every count. Johor has most of the demand and most of the grid and water stress. Selangor and Negeri Sembilan are the second wave. Sarawak is the low-carbon outlier, with hydro power sold by private agreement. Penang has a running site and Kulim’s planned one was cancelled. The table below starts from your constraint.
Two things apply in every state on the Peninsula. Since 24 February 2026 new applications must be AI-related (Malay Mail, 24 Feb 2026), and data centres pay the same TNB tariff wherever they are (Energy Commission). Facts at plot level, such as spare substation capacity and water per site, are not public, so this page compares states. It does not rank plots.
- 4.42 GW
- Johor data-centre demand projected for 2030 (Malay Mail)
- 28%
- Share of requested water granted, 2024 (EdgeProp)
- About 350 MW
- Vena Nexus, Seremban, initial IT load (w.media)
- 0.199 kg CO₂e/kWh
- Sarawak grid emission factor, 2024 (Energy Commission)
Which state fits your constraint?
| If this decides your project | Look first at | Why, and the catch | Published figures |
|---|---|---|---|
| Being where the demand and the operators already are | Johor | The largest share of projected demand. Also the most stress on water and on grid intake. | 4.42 GW Johor data-centre demand projected for 2030 (Malay Mail) 850–1,110 MW Operating capacity, 2026, by broker (JLL) (C&W) 21% Share of requested water granted, 2024 (EdgeProp) |
| Being in the Klang Valley | Selangor | Cyberjaya, Elmina and Banting are the main sites. The state ties approvals to water and power. | 39 Projects approved 2021–2025 (The Star) 1.48 GW Selangor data-centre demand projected for 2030 (Malay Mail) 28% Share of requested water granted, 2024 (EdgeProp) |
| Land between Kuala Lumpur and the coast | Negeri Sembilan | New campuses at Seremban and Port Dickson. Few megawatts are disclosed. | About 350 MW Vena Nexus, Seremban, initial IT load (w.media) 56 MLD Data-centre water approved, 2025–2030 (The Star) |
| Carbon per kWh | Sarawak | A hydro grid. The price is set by private agreement, so it cannot be compared from public data. | 0.199 kg CO₂e/kWh Sarawak grid emission factor, 2024 (Energy Commission) 13.9–26 sen/kWh Published industrial energy charges (Energy Commission) 5 MW Load above which a PPA, not a published tariff, applies (Sarawak Energy) |
| Serving the north | Kedah and Penang | Small capacity running in Penang. The Kulim project was cancelled. | About 15 MW Open DC Bayan Lepas, energised, Sep 2026 (TechWire Asia) 100 MW Open DC Penang target (TechWire Asia) May 2026 Kulim Hi-Tech Park leases rescinded (EdgeProp) |
Each figure is taken from that state’s page, where it is stated with the same source.
Johor: choose it for scale, and plan for water and grid limits
Johor carries most of Malaysia’s data-centre build and most of its projected demand. The limits are water, which the state grants in part, and grid intake. The Johor page sets out both with their sources.
- 4.42 GW Johor data-centre demand projected for 2030 (Malay Mail)
- 850–1,110 MW Operating capacity, 2026, by broker (JLL) (C&W)
- 21% Share of requested water granted, 2024 (EdgeProp)
- RM115–150 Per sq ft in four published Johor land deals (calculation below)
Selangor: choose it for the Klang Valley, if water and power are granted
Selangor counts its projects but publishes no megawatt total. The Menteri Besar has said approvals depend on sufficient water and power (The Star, 8 Sep 2026).
- 39 Projects approved 2021–2025 (The Star)
- 1.48 GW Selangor data-centre demand projected for 2030 (Malay Mail)
- 28% Share of requested water granted, 2024 (EdgeProp)
- 16.23% Air Selangor reserve margin, Aug 2026 (Malay Mail)
Negeri Sembilan: choose it for new land, with less on the record
The projects here are newer and disclose less. Check each project’s megawatts and status before relying on a headline.
- About 350 MW Vena Nexus, Seremban, initial IT load (w.media)
- 56 MLD Data-centre water approved, 2025–2030 (The Star)
- RM3.43bn Two Gamuda build contracts at Port Dickson (Malay Mail) (The Star)
Sarawak: choose it for low-carbon power, and negotiate the price
Sarawak’s grid is hydro-based and outside the Peninsula’s tariff. Loads above 5 MW buy under private power purchase agreements (Sarawak Energy), so there is no published price to compare.
- 0.199 kg CO₂e/kWh Sarawak grid emission factor, 2024 (Energy Commission)
- 13.9–26 sen/kWh Published industrial energy charges (Energy Commission)
- 5 MW Load above which a PPA, not a published tariff, applies (Sarawak Energy)
Kedah and Penang: choose it to serve the north, at small scale
Capacity here is small and the planned Kulim campus did not go ahead.
- About 15 MW Open DC Bayan Lepas, energised, Sep 2026 (TechWire Asia)
- 100 MW Open DC Penang target (TechWire Asia)
- May 2026 Kulim Hi-Tech Park leases rescinded (EdgeProp)
What is the same in every state?
| Factor | What applies | Where to read it |
|---|---|---|
| Who may apply | New applications must be AI-related since 24 February 2026 (Malay Mail, 24 Feb 2026) | What counts as an AI data centre |
| Electricity price, Peninsula | TNB’s HV Ultra time-of-use tariff, the same in every Peninsular state (Energy Commission) | Tariff and all-in cost |
| Grid connection | TNB’s Green Lane Pathway targets 12 months, against 36 to 48 before it (TNB) | Green Lane |
| Booked but unused power | Charged under the Connected Load Charge (TNB) | What unused power costs |
Land prices, flood losses and ten years of hourly climate by district are compared on their own pages: land prices, flood risk and cooling climate.
What is not public
We could not confirm these from a published source as of 15 November 2026. Do not assume them:
- Spare capacity at any substation
- Water available to a given plot
- Flood zoning at plot level
- The price of power under a Sarawak power purchase agreement
- An official megawatt total for Selangor
Sources
- Energy Commission, TNB tariff schedule RP4 (MyEnergyStats copy)
- TNB, charges and penalties (Connected Load Charge)
- TNB, Green Lane Pathway
- Malay Mail, 8.39 GW by 2030 (Oct 2026)
- Malay Mail, new non-AI data centres frozen (24 Feb 2026)
- NST, JLL Johor capacity (Apr 2026)
- EdgeProp, Cushman & Wakefield H1 2026
- EdgeProp, water granted at 21–28% of requests
- The Star, almost 40 data centres approved in Selangor (7 Aug 2026)
- Malay Mail, Selangor exco on data-centre water (6 Aug 2026)
- The Star, MB on approvals subject to water and power (8 Sep 2026)
- The Star, 12.3 GW approved and data-centre water (20 Oct 2026)
- w.media, Negeri Sembilan’s first two data centres (Vena Nexus)
- Malay Mail, Gamuda RM1.72bn Port Dickson contract (17 Apr 2026)
- The Star, Gamuda RM1.71bn Port Dickson job (5 Aug 2026)
- Energy Commission, Sarawak Energy tariffs (MyEnergyStats copy)
- Sarawak Energy, tariff structure for investors
- Energy Commission, grid emission factors 2022–2024 (provisional)
- EdgeProp, Maxland scraps Kulim land deals (15 May 2026)
- TechWire Asia, Open DC Penang to 100 MW (Sep 2026)