Johor, Selangor, Negeri Sembilan, Sarawak or Penang: where should an AI data centre go in Malaysia?

Start from the constraint that decides your project, then read what each state has published. Figures are the ones on each state page, with their sources.

Contents

No state wins on every count. Johor has most of the demand and most of the grid and water stress. Selangor and Negeri Sembilan are the second wave. Sarawak is the low-carbon outlier, with hydro power sold by private agreement. Penang has a running site and Kulim’s planned one was cancelled. The table below starts from your constraint.

Two things apply in every state on the Peninsula. Since 24 February 2026 new applications must be AI-related (Malay Mail, 24 Feb 2026), and data centres pay the same TNB tariff wherever they are (Energy Commission). Facts at plot level, such as spare substation capacity and water per site, are not public, so this page compares states. It does not rank plots.

4.42 GW
Johor data-centre demand projected for 2030 (Malay Mail)
28%
Share of requested water granted, 2024 (EdgeProp)
About 350 MW
Vena Nexus, Seremban, initial IT load (w.media)
0.199 kg CO₂e/kWh
Sarawak grid emission factor, 2024 (Energy Commission)

Which state fits your constraint?

Malaysian states for a data centre, by deciding constraint
If this decides your projectLook first atWhy, and the catchPublished figures
Being where the demand and the operators already areJohorThe largest share of projected demand. Also the most stress on water and on grid intake.4.42 GW Johor data-centre demand projected for 2030 (Malay Mail)
850–1,110 MW Operating capacity, 2026, by broker (JLL) (C&W)
21% Share of requested water granted, 2024 (EdgeProp)
Being in the Klang ValleySelangorCyberjaya, Elmina and Banting are the main sites. The state ties approvals to water and power.39 Projects approved 2021–2025 (The Star)
1.48 GW Selangor data-centre demand projected for 2030 (Malay Mail)
28% Share of requested water granted, 2024 (EdgeProp)
Land between Kuala Lumpur and the coastNegeri SembilanNew campuses at Seremban and Port Dickson. Few megawatts are disclosed.About 350 MW Vena Nexus, Seremban, initial IT load (w.media)
56 MLD Data-centre water approved, 2025–2030 (The Star)
Carbon per kWhSarawakA hydro grid. The price is set by private agreement, so it cannot be compared from public data.0.199 kg CO₂e/kWh Sarawak grid emission factor, 2024 (Energy Commission)
13.9–26 sen/kWh Published industrial energy charges (Energy Commission)
5 MW Load above which a PPA, not a published tariff, applies (Sarawak Energy)
Serving the northKedah and PenangSmall capacity running in Penang. The Kulim project was cancelled.About 15 MW Open DC Bayan Lepas, energised, Sep 2026 (TechWire Asia)
100 MW Open DC Penang target (TechWire Asia)
May 2026 Kulim Hi-Tech Park leases rescinded (EdgeProp)

Each figure is taken from that state’s page, where it is stated with the same source.

Johor: choose it for scale, and plan for water and grid limits

Johor carries most of Malaysia’s data-centre build and most of its projected demand. The limits are water, which the state grants in part, and grid intake. The Johor page sets out both with their sources.

  • 4.42 GW Johor data-centre demand projected for 2030 (Malay Mail)
  • 850–1,110 MW Operating capacity, 2026, by broker (JLL) (C&W)
  • 21% Share of requested water granted, 2024 (EdgeProp)
  • RM115–150 Per sq ft in four published Johor land deals (calculation below)

Everything published on Johor

Selangor: choose it for the Klang Valley, if water and power are granted

Selangor counts its projects but publishes no megawatt total. The Menteri Besar has said approvals depend on sufficient water and power (The Star, 8 Sep 2026).

  • 39 Projects approved 2021–2025 (The Star)
  • 1.48 GW Selangor data-centre demand projected for 2030 (Malay Mail)
  • 28% Share of requested water granted, 2024 (EdgeProp)
  • 16.23% Air Selangor reserve margin, Aug 2026 (Malay Mail)

Everything published on Selangor

Negeri Sembilan: choose it for new land, with less on the record

The projects here are newer and disclose less. Check each project’s megawatts and status before relying on a headline.

  • About 350 MW Vena Nexus, Seremban, initial IT load (w.media)
  • 56 MLD Data-centre water approved, 2025–2030 (The Star)
  • RM3.43bn Two Gamuda build contracts at Port Dickson (Malay Mail) (The Star)

Everything published on Negeri Sembilan

Sarawak: choose it for low-carbon power, and negotiate the price

Sarawak’s grid is hydro-based and outside the Peninsula’s tariff. Loads above 5 MW buy under private power purchase agreements (Sarawak Energy), so there is no published price to compare.

Everything published on Sarawak

Kedah and Penang: choose it to serve the north, at small scale

Capacity here is small and the planned Kulim campus did not go ahead.

Everything published on Kedah and Penang

What is the same in every state?

Factors that do not vary by state
FactorWhat appliesWhere to read it
Who may applyNew applications must be AI-related since 24 February 2026 (Malay Mail, 24 Feb 2026)What counts as an AI data centre
Electricity price, PeninsulaTNB’s HV Ultra time-of-use tariff, the same in every Peninsular state (Energy Commission)Tariff and all-in cost
Grid connectionTNB’s Green Lane Pathway targets 12 months, against 36 to 48 before it (TNB)Green Lane
Booked but unused powerCharged under the Connected Load Charge (TNB)What unused power costs

Land prices, flood losses and ten years of hourly climate by district are compared on their own pages: land prices, flood risk and cooling climate.

What is not public

We could not confirm these from a published source as of 15 November 2026. Do not assume them:

  • Spare capacity at any substation
  • Water available to a given plot
  • Flood zoning at plot level
  • The price of power under a Sarawak power purchase agreement
  • An official megawatt total for Selangor

Sources

Questions

Which Malaysian state is best for a data centre?

It depends on the constraint. Johor has the most demand and the most water and grid stress. Selangor ties approvals to water and power. Negeri Sembilan has newer land with less disclosed. Sarawak has low-carbon hydro power at privately agreed prices. Penang has small running capacity.

Is electricity cheaper for data centres in one Peninsular state than another?

No. Data centres on the Peninsula pay the same TNB HV Ultra tariff in every state. Sarawak is separate: large loads there buy under private power purchase agreements.

Can a non-AI data centre still be approved in Malaysia?

New non-AI data-centre applications have been stopped since 24 February 2026. No written definition of an AI data centre has been published.

Does this page rank individual sites?

No. Spare substation capacity, water per plot and flood zoning at plot level are not public, so only states and zones can be compared.

Looking at a specific site?

We prepare a site feasibility brief that checks power, water, approval and flood questions against the public record and lists what has to be confirmed with TNB, the state and JPS.